Number_of_Days_Late__c |
Number of Days Late |
Summer 2023 |
Formula field. This field calculates whether the Supplier Commitment Date is before today's date.
Formula: IF(SCMC__Supplier_Commitment_Date__c > TODAY(),0, TODAY() - SCMC__Supplier_Commitment_Date__c)
|
Number(18,0) |
|
Number_of_expected_days_late__c |
Number of expected days late |
Summer 2023 |
Formula field. This field computes if the Current Promise date is later than supplier commitment date.
Formula: IF(SCMC__Supplier_Current_Promise_Date__c > SCMC__Supplier_Commitment_Date__c, SCMC__Supplier_Current_Promise_Date__c - SCMC__Supplier_Commitment_Date__c, 0)
|