Professional Services Automation Data Dictionary

Project_Task_Dependency__c

Label: Project Task Dependency

Specifies a relationship between two project tasks. If a project task is completed early or late, this has an effect on the start and end date of the task that succeeds it. You can create four standard types of dependency. Dependent tasks have a master-detail relationship with project task dependencies.

Field NameField LabelCreated in VersionDescriptionTypeDefault Value
Cross_Project__c Cross Project Pre-Spring 2018 Indicates if this link between two tasks spans two projects

Checkbox false
Dependency_Display_Units__c Dependency Display Units Pre-Spring 2018 Specifies the units of time used for project tasks. Valid values are hours or days. The default value is days.

Text(10)
Dependent_Task_End_Date_Time__c Dependent Task End Date & Time Pre-Spring 2018 Formula:
Dependent_Task__r.End_Date_Time__c
DateTime
Dependent_Task_End_Date__c Dependent Task End Date Pre-Spring 2018 Formula:
Dependent_Task__r.End_Date__c
Date
Dependent_Task_Start_Date_Time__c Dependent Task Start Date & Time Pre-Spring 2018 Formula:
Dependent_Task__r.Start_Date_Time__c
DateTime
Dependent_Task_Start_Date__c Dependent Task Start Date Pre-Spring 2018 Formula:
Dependent_Task__r.Start_Date__c
Date
Dependent_Task__c Dependent Task Pre-Spring 2018 This master-detail lookup references the Project Task that is the dependent Task in this relationship.

Looks up to: Project_Task__c
MasterDetail
Lag_Time_Hours__c Lag Time Pre-Spring 2018 Number(18,0)
Lag_Units__c Lag Units Pre-Spring 2018 Displays the lag unit type as either hours or days.

Formula:
$Setup.Project_Task_Gantt_Global_Settings__c.Task_Dependancy_Lag_Designation__c
Text
New_Dependency_Record__c New Dependency Record Pre-Spring 2018 Indicates if this record contains updated lag unit ignoring custom setting

Checkbox true
Preceding_Task_End_Date_Time__c Preceding Task End Date & Time Pre-Spring 2018 Formula:
Preceding_Task__r.End_Date_Time__c
DateTime
Preceding_Task_End_Date__c Preceding Task End Date Pre-Spring 2018 Formula:
Preceding_Task__r.End_Date__c
Date
Preceding_Task_Start_Date_Time__c Preceding Task Start Date & Time Pre-Spring 2018 Formula:
Preceding_Task__r.Start_Date_Time__c
DateTime
Preceding_Task_Start_Date__c Preceding Task Start Date Pre-Spring 2018 Formula:
Preceding_Task__r.Start_Date__c
Date
Preceding_Task__c Preceding Task Pre-Spring 2018 This lookup references the Project Task that is the preceding Task in this relationship.

Looks up to: Project_Task__c
Lookup
Project__c Project Pre-Spring 2018 Formula:
Dependent_Task__r.Project__c
Text
Type__c Type Pre-Spring 2018 Picklist:
Finish to Finish (FF)
Finish to Start (FS)
Start to Finish (SF)
Start to Start (SS)


© Copyright 2009–2024 Certinia Inc. All rights reserved. Various trademarks held by their respective owners.