Professional Services Automation Data Dictionary

Schedule__c

Label: Schedule

Represents start and end dates and weekly working hours for an assignment. You enter schedule details when you create an assignment, which also creates an associated schedule record. Although schedule records have the fields Scheduled Hours and Scheduled Days, these are not intended for users to enter time directly. Their values are system-generated based on schedule dates, patterns, and exceptions. Specific deviations from schedules are represented as schedule exceptions.

Field NameField LabelCreated in VersionDescriptionTypeDefault Value
Action_Force_Schedule_Refresh__c Action: Force Schedule Refresh Pre-Spring 2018 If checked on save, refreshes Scheduled Hours, Assignment Projected Revenue and Est Vs Actuals records related to Schedule/Assignment.

Checkbox false
Action_Update_Future_Scheduled_Hours__c Action: Update Future Scheduled Hours Pre-Spring 2018 If checked on save, refreshes Future Scheduled Hours

Checkbox false
End_Date__c End Date Pre-Spring 2018 Schedule end date.

Date
Friday_End_Time__c Friday End Time Pre-Spring 2018 Indicates that Friday End Time is the scheduled end time for the indicated day.

DateTime
Friday_Hours__c Friday Hours Pre-Spring 2018 Friday hours on schedule

Number(4,2) 0
Friday_Start_Time__c Friday Start Time Pre-Spring 2018 Indicates that Friday Start Time is the scheduled start time for the indicated day.

DateTime
Future_Scheduled_Hours_Last_Updated__c Future Scheduled Hours Last Update Date Pre-Spring 2018 The last updated date for Future Scheduled Hours calculation.

DateTime
Future_Scheduled_Hours__c Future Scheduled Hours Pre-Spring 2018 Total number of scheduled hours remaining.

Number(12,2)
Is_Blocking__c Is Blocking Pre-Spring 2018 If selected, this schedule blocks other assignments created with the Team Schedule Planner application.

Checkbox false
Monday_End_Time__c Monday End Time Pre-Spring 2018 Monday End Time is the scheduled end time on the indicated day.

DateTime
Monday_Hours__c Monday Hours Pre-Spring 2018 Monday hours on schedule

Number(4,2) 0
Monday_Start_Time__c Monday Start Time Pre-Spring 2018 Monday Start Time is the scheduled start time on the indicated day.

DateTime
Saturday_End_Time__c Saturday End Time Pre-Spring 2018 Saturday End Time is the scheduled end time on the indicated day.

DateTime
Saturday_Hours__c Saturday Hours Pre-Spring 2018 Saturday hours on schedule

Number(4,2) 0
Saturday_Start_Time__c Saturday Start Time Pre-Spring 2018 SaturdayStart Time is the scheduled start time on the indicated day.

DateTime
Scheduled_Days__c Scheduled Days Pre-Spring 2018 Number of days scheduled

Number(18,6) 0
Scheduled_Hours__c Scheduled Hours Pre-Spring 2018 Total number of hours scheduled.

Number(12,2)
Start_Date__c Start Date Pre-Spring 2018 Schedule start date.

Date
Sunday_End_Time__c Sunday End Time Pre-Spring 2018 Sunday End Time is the scheduled end time on the indicated day.

DateTime
Sunday_Hours__c Sunday Hours Pre-Spring 2018 Sunday hours on schedule

Number(4,2) 0
Sunday_Start_Time__c Sunday Start Time Pre-Spring 2018 Sunday Start Time is the scheduled start time on the indicated day.

DateTime
Thursday_End_Time__c Thursday End Time Pre-Spring 2018 Thursday End Time is the scheduled end time on the indicated day.

DateTime
Thursday_Hours__c Thursday Hours Pre-Spring 2018 Thursday hours on schedule

Number(4,2) 0
Thursday_Start_Time__c Thursday Start Time Pre-Spring 2018 Thursday Start Time is the scheduled start time on the indicated day.

DateTime
Tuesday_End_Time__c Tuesday End Time Pre-Spring 2018 Tuesday End Time is the scheduled end time on the indicated day.

DateTime
Tuesday_Hours__c Tuesday Hours Pre-Spring 2018 Tuesday hours on schedule

Number(4,2) 0
Tuesday_Start_Time__c Tuesday Start Time Pre-Spring 2018 Tuesday Start Time is the scheduled start time on the indicated day.

DateTime
Wednesday_End_Time__c Wednesday End Time Pre-Spring 2018 Wednesday End Time is the scheduled end time on the indicated day.

DateTime
Wednesday_Hours__c Wednesday Hours Pre-Spring 2018 Wednesday hours on schedule

Number(4,2) 0
Wednesday_Start_Time__c Wednesday Start Time Pre-Spring 2018 Wednesday Start Time is the scheduled start time on the indicated day.

DateTime
Week_Total_Hours__c Week Total Hours Pre-Spring 2018 The total of the daily hours

Formula:
Sunday_Hours__c + Monday_Hours__c + Tuesday_Hours__c + Wednesday_Hours__c + Thursday_Hours__c + Friday_Hours__c + Saturday_Hours__c
Number(18,2)


© Copyright 2009–2024 Certinia Inc. All rights reserved. Various trademarks held by their respective owners.