| pse__Adjust_Past_Est_on_Records_with_Actuals__c |
Adjust Past Est on Records with Actuals |
Pre-Spring 2018 |
|
Checkbox |
|
false |
| pse__Calculate_EVA_Actuals_Incrementally__c |
Calculate EVA Actuals Incrementally |
Summer 2024 |
If selected, only modified timecards are considered for calculating EVA Actuals using incremental calculation and will not perform a complete calculation. By default, it is selected.
|
Checkbox |
|
true |
| pse__Delete_Dated_Rate_Change_Batch_Size__c |
Delete DRR Change Records Batch Size |
Summer 2025 |
Defines the batch size used when deleting Dated Resource Rate Change records after processing. The default is 5000. Consult with Certinia customer support before changing this setting.
|
Number(5,0) |
false |
5000 |
| pse__Delete_Est_Vs_Actuals_Batch_Size__c |
Delete Est Vs Actuals Batch Size |
Pre-Spring 2018 |
|
Number(8,0) |
false |
2000 |
| pse__Delete_Out_of_Range_Records_With_Actuals__c |
Delete Out of Range Records With Actuals |
Pre-Spring 2018 |
Delete Est vs Actuals records even if they have actuals set for records that are no longer within a modified schedule's date range. NOTE: Records without actuals will always be deleted.
|
Checkbox |
|
false |
| pse__Enable_Eva_Process_Custom_Notification__c |
Enable EVA Process Custom Notification |
Summer 2025 |
If selected, enables custom bell notifications for the async process of Bulk Update EVAs for Dated Resource Rate Changes. By default, it is deselected.
|
Checkbox |
|
false |
| pse__Enable_Eva_Process_Notification__c |
Enable EVA Process Notification |
Summer 2024 |
If selected, EVA job execution will be notified through a toast message. By default, it is deselected.
|
Checkbox |
|
false |
| pse__Generate_Custom_Time_Period_Records__c |
Generate Custom Time Period Records |
Pre-Spring 2018 |
Comma separated list of time period types for which to generate EVA records
|
Text(255) |
false |
|
| pse__Generate_Monthly_Records__c |
Generate Monthly Records |
Pre-Spring 2018 |
|
Checkbox |
|
false |
| pse__Generate_Quarterly_Records__c |
Generate Quarterly Records |
Pre-Spring 2018 |
|
Checkbox |
|
false |
| pse__Generate_Weekly_Records__c |
Generate Weekly Records |
Pre-Spring 2018 |
|
Checkbox |
|
true |
| pse__Process_Out_Of_Range_Timecards__c |
Process Out Of Range Timecards |
Pre-Spring 2018 |
Create Est Vs Actuals records for timecards that have hours outside of the assignment's start and end date. The Est Vs Actuals records will have zero values for estimates on these records.
|
Checkbox |
|
false |
| pse__Sync_Assignment_EVAs_To_DRR_Job_Size__c |
(Beta) Sync Assign EVAs to DRR: Job Size |
Spring 2025 |
The number of assignments processed per job by the asynchronous process which updates EVAs to reflect dated resource rate changes. The default is 200.
|
Number(8,0) |
false |
200 |
| pse__Sync_Assignment_EVAs_To_DRR_Max_Jobs__c |
(Beta) Sync Assign EVAs to DRR: Max Jobs |
Spring 2025 |
The maximum number of jobs that will be run at once by the asynchronous process which updates EVAs to reflect dated resource rate changes. This value, in conjunction with Sync Assignment EVAs to DRR: Job Size, will determine how many assignments are queried at a time. It defaults to blank (meaning unlimited) but can be configured if the asynchronous process is found to be blocking other processes from running at the same time.
|
Number(8,0) |
false |
|
| pse__Sync_Res_Req_EVAs_To_DRR_Job_Size__c |
(Beta) Sync ResReq EVAs to DRR: Job Size |
Summer 2025 |
The number of resource requests processed per job by the asynchronous process which updates EVAs to reflect dated resource rate changes. The default is 200.
|
Number(8,0) |
false |
200 |
| pse__Sync_Res_Req_EVAs_To_DRR_Max_Jobs__c |
(Beta) Sync ResReq EVAs to DRR: Max Jobs |
Summer 2025 |
The maximum number of jobs that will be run at once by the asynchronous process which updates EVAs to reflect dated resource rate changes. This value, in conjunction with Sync ResReq EVAs to DRR: Job Size, will determine how many resource requests are queried at a time. It defaults to blank (meaning unlimited) but can be configured if the asynchronous process is found to be blocking other processes from running at the same time.
|
Number(8,0) |
false |
|
| pse__Timecard_Statuses__c |
Timecard Statuses |
Pre-Spring 2018 |
|
Text(255) |
false |
'Submitted,Approved' |
| pse__Update_Actuals_Batch_Size__c |
Update Actuals Batch Size |
Pre-Spring 2018 |
|
Number(8,0) |
false |
2000 |
| pse__Update_Estimates_Batch_Size__c |
Update Estimates Batch Size |
Pre-Spring 2018 |
|
Number(8,0) |
false |
2000 |
| pse__Update_Project_Manager_Batch_Size__c |
Update Project Manager Field Batch Size |
Pre-Spring 2018 |
Defines the batch size used when updating the Project Manager field from Project. The default is 2000. Consult with Certinia customer support before changing this setting.
|
Number(8,0) |
false |
2000 |
| pse__Update_Project_Manager_From_Project__c |
Update Project Manager From Project |
Pre-Spring 2018 |
If checked, this setting causes updates to the Project Manager field to be reflected in all Est Vs Actuals records for that Project.
|
Checkbox |
|
true |
| pse__Update_Project_Manager_Sync_Limit__c |
Update Project Manager Field Sync Limit |
Pre-Spring 2018 |
Defines the number of Est Vs Actuals records to process synchronously when updating the Project Manager field from Project. Records in excess of this value are processed in a batch. The default is 9000. Consult with Support before changing this setting.
|
Number(8,0) |
false |
9000 |
| pse__Use_Week_Time_Periods_If_In_Range__c |
Disable Automatic Weekly Time Periods |
Pre-Spring 2018 |
When true, weekly estimates versus actuals are not automatically generated if you have custom time periods of a week type defined that overlap with an assignment or a held resource request. The default value is false.
|
Checkbox |
|
false |