| pse__Action_Sync_With_External_Calendar__c |
Action: Sync with External Calendar |
Spring 2023 |
Checkbox to sync PTA with external calendar.
|
Checkbox |
|
false |
| pse__Actual_Cost__c |
Actual Cost |
Spring 2023 |
The actual cost of the project task assignment, which is calculated by multiplying its timecard actual hours by the cost rate of the assigned resources.
|
Currency(18,2) |
false |
0.00 |
| pse__Allocation_Hours__c |
Allocation Hours |
Fall 2019 |
The number of hours allocated to a resource for a project task assignment.
|
Number(7,2) |
false |
|
| pse__Allocation_Percentage__c |
Allocation Percentage |
Spring 2019 |
The percentage resource and/or role allocation of the task's estimated hours.
|
Percent(5,2) |
false |
|
| pse__Assignment__c |
Assignment |
Pre-Spring 2018 |
Looks up to: pse__Assignment__c
|
Lookup |
false |
|
| pse__End_Date__c |
End Date |
Pre-Spring 2018 |
Formula: IF( NOT(ISBLANK(pse__Assignment__c)), pse__Assignment__r.pse__End_Date__c, IF(NOT(ISBLANK(pse__Resource_Request__r.pse__Preferred_Schedule__c)), pse__Resource_Request__r.pse__Preferred_Schedule__r.pse__End_Date__c, pse__Resource_Request__r.pse__End_Date__c ) )
|
Date |
false |
|
| pse__Estimated_Cost__c |
Estimated Cost |
Spring 2023 |
The estimated cost of the project task assignment, calculated from the allocated hours and the default cost rates of the assigned resources.
|
Currency(18,2) |
false |
0.00 |
| pse__Estimated_Hours__c |
Estimated Hours |
Spring 2023 |
The hours allocated to the resource on the project task assignment.
|
Number(18,2) |
false |
|
| pse__Exclude_From_External_Calendar_Sync__c |
Exclude from External Calendar Sync |
Spring 2023 |
When selected, the project task assignment is not synced with an external calendar and the existing calendar events are also deleted if any.
|
Checkbox |
|
false |
| pse__External_Resource__c |
External Resource |
Pre-Spring 2018 |
|
Text(255) |
false |
|
| pse__Hours__c |
Hours |
Pre-Spring 2018 |
The number of scheduled hours.
Formula: IF( AND(NOT(ISBLANK(pse__Assignment__c)), NOT(ISBLANK(pse__Assignment__r.pse__Scheduled_Hours__c)) ), pse__Assignment__r.pse__Scheduled_Hours__c, IF( NOT(ISBLANK(pse__Resource_Request__c)), IF( AND( NOT(ISBLANK(pse__Resource_Request__r.pse__Preferred_Schedule__c)), NOT(ISBLANK( pse__Resource_Request__r.pse__Preferred_Schedule__r.pse__Scheduled_Hours__c)) ), pse__Resource_Request__r.pse__Preferred_Schedule__r.pse__Scheduled_Hours__c, IF( NOT(ISBLANK(pse__Resource_Request__r.pse__SOW_Hours__c)), pse__Resource_Request__r.pse__SOW_Hours__c, 0) ), 0) )
|
Number(18,2) |
false |
|
| pse__Project_ID__c |
Project ID |
Pre-Spring 2018 |
Formula: pse__Project_Task__r.pse__Project__c
|
Text |
false |
|
| pse__Project_Task_End_Date__c |
Project Task End Date |
Pre-Spring 2018 |
Formula: pse__Project_Task__r.pse__End_Date__c
|
Date |
false |
|
| pse__Project_Task_Start_Date__c |
Project Task Start Date |
Pre-Spring 2018 |
Formula: pse__Project_Task__r.pse__Start_Date__c
|
Date |
false |
|
| pse__Project_Task__c |
Project Task |
Pre-Spring 2018 |
Project Task to which the Resource is being Associated
Looks up to: pse__Project_Task__c
|
MasterDetail |
|
|
| pse__Project__c |
Project |
Pre-Spring 2018 |
Formula: IF(OR(ISNULL(pse__Project_Task__c),(pse__Project_Task__c=''),ISNULL(pse__Project_Task__r.pse__Project__c),(pse__Project_Task__r.pse__Project__c='')),'',HYPERLINK('/'&pse__Project_Task__r.pse__Project__c,IF(OR(ISNULL(pse__Project_Task__r.pse__Project__r.Name),(pse__Project_Task__r.pse__Project__r.Name='')),pse__Project_Task__r.pse__Project__c,pse__Project_Task__r.pse__Project__r.Name)))
|
Text |
false |
|
| pse__Resource_Request__c |
Resource Request |
Pre-Spring 2018 |
Looks up to: pse__Resource_Request__c
|
Lookup |
false |
|
| pse__Resource_Role__c |
Resource Role |
Pre-Spring 2018 |
|
Picklist: Architect Business Analyst Client Manager Consultant Contractor Executive Project Manager Senior Consultant Trainer |
false |
|
| pse__Resource__c |
Resource |
Pre-Spring 2018 |
Resource being associated with the Project Task
Looks up to: Contact
|
Lookup |
false |
|
| pse__Schedule_Type__c |
Schedule Type |
Pre-Spring 2018 |
Formula: IF( NOT(ISBLANK(pse__Assignment__c)), $Label.pta_schedule_type_assignment, IF(NOT(ISBLANK(pse__Resource_Request__c)), IF(NOT(ISBLANK(pse__Resource_Request__r.pse__Preferred_Schedule__c)), $Label.pta_schedule_type_rr_schedule, $Label.pta_schedule_type_rr_dates ), $Label.pta_schedule_type_rr_none ) )
|
Text |
false |
|
| pse__Start_Date__c |
Start Date |
Pre-Spring 2018 |
Formula: IF( NOT(ISBLANK(pse__Assignment__c)), pse__Assignment__r.pse__Start_Date__c, IF(NOT(ISBLANK(pse__Resource_Request__r.pse__Preferred_Schedule__c)), pse__Resource_Request__r.pse__Preferred_Schedule__r.pse__Start_Date__c, pse__Resource_Request__r.pse__Start_Date__c ) )
|
Date |
false |
|