Objective_KPI__c
Label: Objective KPI Stores the key performance indicator records that were created for objectives.
Baseline_Value__c |
Baseline Value |
Summer 2024 |
The starting value of the objective key performance indicator.
|
Number(18,4) |
|
Category__c |
Category |
August 2024 |
The category of the objective key performance indicator.
|
Picklist: Approval on Time Budget Variance Completion on Time Customer Satisfaction Project Margin Reduced Timecard Errors and Time to Bill Resource Management Margin Skill Capacity Time to Staff Timecards Submitted on Time Utilization |
|
Current_Value__c |
Current Value |
Summer 2024 |
The current value of the objective key performance indicator.
|
Number(18,4) |
|
Description__c |
Description |
Summer 2024 |
The description of the objective key performance indicator.
|
Text(255) |
|
Objective__c |
Objective |
Summer 2024 |
The objective that the objective key performance indicator is associated with.
Looks up to: Objective__c
|
Lookup |
|
Progress__c |
Progress |
October 2024 |
Calculates the percent completion of the objective KPI.
Formula: IF(OR(ISNULL(Target_Value__c),ISNULL(Current_Value__c)) , NULL , IF(BLANKVALUE(Baseline_Value__c, 0) = Target_Value__c , IF(Current_Value__c < Target_Value__c, 0, 1) , MAX( MIN( (Current_Value__c - BLANKVALUE(Baseline_Value__c, 0)) / (Target_Value__c - BLANKVALUE(Baseline_Value__c, 0)) , 1) , 0) ) )
|
Percent(18,2) |
|
Target_Date__c |
Target Date |
Summer 2024 |
The target date of the objective key performance indicator.
|
Date |
|
Target_Value__c |
Target Value |
Summer 2024 |
The target value of the objective key performance indicator.
|
Number(18,4) |
|
Unit__c |
Unit |
Summer 2024 |
The unit of measurement for the baseline, current, and target values of the objective key performance indicator.
|
Picklist: Days EUR GBP Hours JPY Months Percent Quantity USD Weeks |
|
|