Mass Linking Project Task Assignments
PSA enables you to link multiple project task assignments, to a resource request or an assignment, or both.
To link project task assignments:
- On a project record, click Actions | Task-Based Resourcing | Mass Link Project Task Assignments.
- From the lookups, select the resource request or assignment, or both that you want to link the assignments to.
- The Resource, Role, Start Date and End Date are read only fields, automatically populated with the details of the resource request or the assignment selected from the lookups.
- [Optional] Select filter criteria to determine the project task assignments shown. Click Apply. The project task assignments that meet your criteria are displayed. See Mass Link Project Task Assignment Fields in Lightning for more information.
- Select the project task assignments you want to link.
- Click Link Project Task Assignments.