How Renewal Dates are Calculated

When creating a renewal, you can choose whether the original contract's duration is replicated in days or in months. For example, if you choose to renew using days, and the original contract's duration is 30 days then each renewal for that contract will be 30 days.

If you choose to renew using months:

  • Rule A - Where the original contract's start date and the renewal's start date fall on the same day of the month, calculate the renewal's end date so that the next renewal also starts on that day of the month.

    In scenarios where this cannot be calculated, Billing Central tries to apply Rule B. For example, if a monthly contract starts on July 31 the first renewal can start on August 31, but the second renewal cannot start on September 31 because that date does not exist. In this scenario, Billing Central tries to apply Rule B.

  • Rule B - Where the original contract's start date and the renewal's start date fall on the same number of days before the end of the month, calculate the renewal's end date so that the next renewal also starts that many days before the end of the month.
  • Rule C - For scenarios that do not comply with Rule A or B, replicate the original contract's duration using days.
Note:

When renewing a contract from the enhanced Billing Contract Detail page, you cannot choose whether the duration is replicated as months or days. The default set by the Renew Contract Duration as Months field in the Billing Central Settings custom setting is used.

Illustration of Rule A

Contract X has a duration of 31 days (January 10, 2019 to February 9, 2019). Renewal 1 starts on February 10, 2019. When renewing as days, Renewal 1 ends on March 12, 2019 (31 days from the start date). When renewing as months, Renewal 1 ends on March 9 so that Renewal 2 can start on March 10.

 

 

Renew as Days

Renew as Months

Contract X Start Date January 10, 2019 January 10, 2019
  End Date February 9, 2019 February 9, 2019
Renewal 1 Start Date February 10, 2019 February 10, 2019
  End Date March 12, 2019 March 9, 2019
Renewal 2 Start Date March 13, 2019 March 10, 2019
  End Date April 12, 2019 April 9, 2019
Renewal 3 Start Date April 13, 2019 April 10, 2019
  End Date May 13, 2019 May 9, 2019
Renewal 4 Start Date May 14, 2019 May 10, 2019
  End Date June 13, 2019 June 9, 2019

Illustration of Rule B

Contract Y has a duration of 28 days (January 31, 2019 to February 27, 2019). Renewal 1 starts on February 28, 2019. When renewing as days, Renewal 1 ends on March 27, 2019 (28 days from the start date). When renewing as months, Renewal 1 ends on March 30, 2019 so that Renewal 2 can start on the last day of the month.

 

 

Renew as Days

Renew as Months

Contract Y Start Date January 31, 2019 January 31, 2019
  End Date February 27, 2019 February 27, 2019
Renewal 1 Start Date February 28, 2019 February 28, 2019
  End Date March 27, 2019 March 30, 2019
Renewal 2 Start Date March 28, 2019 March 31, 2019
  End Date April 24, 2019 April 29, 2019
Renewal 3 Start Date April 25, 2019 April 30, 2019
  End Date May 22, 2019 May 30, 2019
Renewal 4 Start Date May 23, 2019 May 31, 2019
  End Date June 19, 2019 June 29, 2019

Illustration of Rule C

Contract Z has a duration of 12 weeks (January 1, 2019 to March 26, 2019). Renewal 1 starts on March 27, 2019. Because the contract's start date and the renewal's start date neither fall on the same day of the month, nor fall on the same number of days before the end of the month, the renewal duration is calculated using the contract's duration in days which is 85.