Viewing Project Details

The Project Details view of the PSA Project Scheduling Risk dashboard displays information specific to one project, which can be drilled down to the resource or role level for the last 13 weeks or next 13 weeks. The Project Details view enables you to:

  • Toggle to view information for the Last 13 Weeks and Next 13 Weeks of the project.
  • In the Last 13 Weeks or Next 13 Weeks tab, toggle to view information at Resource and Role level.
  • View the hours information for resources and roles by hovering over the bars in the bar chart.
    Note: The role's bill rate is calculated by weighted average bill rate, as a resource could have multiple assignments for different roles and so can have multiple bill rates. Therefore, the Average Bill Rate refers to the average bill rate of all resources assigned to the role for the project weighted by the hours worked.

Resource Analytics - Last 13 Weeks

The Resource view of the Last 13 Weeks dashboard has the following elements.

Project Details view of the PSA Project Scheduling Risk dashboard highilghting the key elements of the resource view for the last 13 weeks.

Role Analytics - Last 13 Weeks

The Role view of the Last 13 Weeks dashboard has the following elements.

Project Details view of the PSA Project Scheduling Risk dashboard highilghting the key elements of the role view for the last 13 weeks.

Resource Analytics - Next 13 Weeks

The Resource view of the Next 13 Weeks dashboard has the following elements.

Project Details view of the PSA Project Scheduling Risk dashboard highilghting the key elements of the resource view for the next 13 weeks.

Role Analytics - Next 13 Weeks

The Role view of the Next 13 Weeks dashboard has the following elements.

Project Details view of the PSA Project Scheduling Risk dashboard highilghting the key elements of the role view for the next 13 weeks.

Element Number Name Description Calculation Referenced Calculation Source Dataset
1.

Project Details

Displays the following information about the selected project:

  • Project Name
  • Billing Type
  • Project Progress, which is expressed as a percentage, along with the start and end date of the project
  • Account
  • PM

If you have planned hours for the project, then project progress percentage is calculated as:

Total Submitted hours / Planned Hours

If you don't have planned hours for the project, then project progress percentage = Project Percent Hours Complete

   
Resource Analytics - Last 13 Weeks
2.

Detailed Analytics

Displays variance information for the last 13 week as follows:

  • Total Hours Variance %, which is the difference between the scheduled and actual hours for the last 13 weeks
  • Total Revenue Variance, which is the difference between the estimated and actual revenue for the last 13 weeks

Total Hours Variance % = (Actual Hours - Scheduled Hours) / Scheduled Hours

 

Total Revenue Variance = Last 13 weeks Actual Revenue - Last 13 weeks Estimated Revenue

Total Hours % Variance = (EvA Actual Hours - EvA Estimated Hours) / EvA Estimated Hours

or

EvA Hours Variance / EvA Estimated Hours

 

Total Revenue Variance = EvA Actual Billable Amount - EvA Scheduled Amount

 
3a.

Resource Analytics - Bar Chart - Last 13 Weeks 

Displays the actual and scheduled hours for each resource assigned to the project for the last 13 weeks in a bar chart. The resource with the greatest variance in actual versus scheduled hours is listed furthest left. Click on the bars for each resource to get the total hours variance % and total revenue variance.

     
3b.

Resource Analytics - Hours Variance Trend - Last 13 Weeks 

Displays the actual and scheduled hours for the project for the last 13 weeks in a line chart.

     
3c. Chart Legend Legend for the information displayed in the bar and line charts, which consists of actual and scheduled hours information for the resources assigned to the project, and for the project overall. Actual Hours = EvA Actual Hours

 

Scheduled Hours = EvA Estimated Hours

   
Role Analytics - Last 13 Weeks
4. Detailed Analytics

Displays variance information for the last 13 week as follows:

  • Total Hours Variance %, which is the difference between the scheduled and actual hours for the last 13 weeks
  • Total Revenue Variance, which is the difference between the estimated and actual revenue for the last 13 weeks

Total Hours Variance % = (Actual Hours - Scheduled Hours) / Scheduled Hours

 

Total Revenue Variance = Last 13 weeks Actual Revenue - Last 13 weeks Estimated Revenue

Total Hours % Variance = (EvA Actual Hours - EvA Estimated Hours) / EvA Estimated Hours

or

EvA Hours Variance / EvA Estimated Hours

 

Total Revenue Variance = EvA Actual Billable Amount - EvA Scheduled Amount

 
5a.

Role Analytics - Bar Chart - Last 13 Weeks 

Displays the actual and scheduled hours for each project role for the last 13 weeks in a bar chart. The role with the greatest variance in actual versus scheduled hours is listed furthest left. Click on the bars for each role to get the total hours variance % and total revenue variance.

     
5b.

Role Analytics - Hours Variance Trend - Last 13 Weeks 

Displays the actual and scheduled hours for the project for the last 13 weeks in a line chart.

     
5c. Chart Legend Legend for the information displayed in the bar and line charts, which consists of actual and scheduled hours information for the project roles, and for the project overall. Actual Hours = EvA Actual Hours

 

Scheduled Hours = EvA Estimated Hours

   
Resource Analytics - Next 13 Weeks
6. Detailed Analytics

Displays predicted variance information for the next 13 week as follows:

  • Predicted Hours Variance %, which is the difference between the scheduled and predicted hours for the next 13 weeks
  • Predicted Revenue Variance, which is the difference between the estimated and predicted revenue for the next 13 weeks

Predicted Hours Variance % = Predicted Hours Variance / Scheduled Hours

 

Predicted Revenue Variance = Predicted Revenue - Estimated Revenue

Predicted Hours Variance = EvA Estimated Hours (future) * (EvA Hours Variance (past) / EvA Estimated Hours (past))

 

Scheduled Hours = EvA Estimated Hours

 

Predicted Revenue = EvA Scheduled Amount * Average Variance % for the last 13 weeks

 

Estimated Revenue = EvA Scheduled Amount

 
7a.

Resource Analytics - Bar Chart - Next 13 Weeks

Displays the predicted and scheduled hours for each resource assigned to the project for the next 13 weeks in a bar chart. Predicted hours are based on the actual hours for the resource for the last 13 weeks. The resource with the greatest variance in predicted versus scheduled hours is listed furthest left. Click on the bars for each resource to get the predicted hours variance % and predicted revenue variance.

     
7b.

Resource Analytics - Hours Variance Trend - Next 13 Weeks

Displays the predicted and scheduled hours for the project for the next 13 weeks in a line chart. Predicted hours are based on the actual hours for the project for the last 13 weeks.

     
7c. Chart Legend Legend for the information displayed in the bar and line charts, which consists of predicted and scheduled hours information for the resources assigned to the project, and for the project overall. Predicted Hours = EVA Estimated Hours - (Average Variance % for last 13 weeks * EVA Estimated Hours)

 

Scheduled Hours = EvA Estimated Hours

   
Role Analytics - Next 13 Weeks
8. Detailed Analytics

Displays predicted variance information for the next 13 week as follows:

  • Predicted Hours Variance %, which is the difference between the scheduled and predicted hours for the next 13 weeks
  • Predicted Revenue Variance, which is the difference between the estimated and predicted revenue for the next 13 weeks

Predicted Hours Variance % = Predicted Hours Variance / Scheduled Hours

 

Predicted Revenue Variance = Predicted Revenue - Estimated Revenue

Predicted Hours Variance = EvA Estimated Hours (future) * (EvA Hours Variance (past) / EvA Estimated Hours (past))

 

Scheduled Hours = EvA Estimated Hours

 

Predicted Revenue = EvA Scheduled Amount * Average Variance % for the last 13 weeks

 

Estimated Revenue = EvA Scheduled Amount

 
9a.

Role Analytics - Bar Chart  - Next 13 Weeks 

Displays the predicted and scheduled hours for each project role for the next 13 weeks in a bar chart. Predicted hours are based on the actual hours for the resource for the last 13 weeks. The role with the greatest variance in predicted versus scheduled hours is listed furthest left. Click on the bars for each role to get the predicted hours variance % and predicted revenue variance.

     
9b.

Role Analytics - Hours Variance Trend  - Next 13 Weeks 

Displays the predicted and scheduled hours for the project for the next 13 weeks in a line chart. Predicted hours are based on the actual hours for the project for the last 13 weeks.

     
9c.

Chart Legend

Legend for the information displayed in the bar and line charts, which consists of predicted and scheduled hours information for the project roles, and for the project overall.

Predicted Hours = EVA Estimated Hours - (Average Variance % for last 13 weeks * EVA Estimated Hours)

 

Scheduled Hours = EvA Estimated Hours