Schedule Fields

Here is a description of the fields that make up a Schedule record.

Key:
* – Mandatory field
R – Read-only

Field   Description
Action: Force Reschedule Refresh   If checked when you save, Scheduled Hours, Assignment Projected Revenue, and Est Vs Actuals records related to Schedules and Assignments refresh.
Action: Update Future Scheduled Hours   If checked when you save, Future Scheduled Hours refresh.
End Date   Schedule end date.
Future Scheduled Hours   The total number of remaining scheduled hours.
Future Scheduled Hours Last Updated Date   The last updated date for Future Scheduled Hours calculation.
Is Blocking  

If selected, this schedule blocks other assignments created with the Team Schedule Planner application.

Note:

This setting supports blocking Shift Management (Time of Day) schedules imported by custom integrations.

Monday Hours   Default number of hours to be scheduled on each day. These are used when creating a new resource schedule.
Tuesday Hours  
Wednesday Hours  
Thursday Hours  
Friday Hours  
Saturday Hours  
Sunday Hours  
Scheduled Days R The number of scheduled days.
Scheduled Hours R The number of scheduled hours.
Start Date    
Week Total Hours R Formula field displayed to two decimal places showing the sum of daily hours for a resource in a week. calculated from the Schedule object.
Monday Start Time   The start time for the indicated day.
Tuesday Start Time  
Wednesday Start Time  
Thursday Start Time  
Friday Start Time  
Saturday Start Time  
Sunday Start Time  
Monday End Time   The end time for the indicated day.
Tuesday End Time  
Wednesday End Time  
Thursday End Time  
Friday End Time  
Saturday End Time  
Sunday End Time  

Lightning Quick Action Buttons

Quick Action Description
Zero Schedule Allows you to reset the schedule for the resource to zero.