Calculating Future Scheduled Hours

To calculate Future Scheduled Hours for assignments:

Note:

Calculating Future Scheduled Hours requires fields to be added to the Schedule page layout. For more information, see Customizing Page Layouts.

For an individual schedule:

  1. On the Schedule Detail page, check Action: Update Future Scheduled Hours.
  2. Click Save.

Updated hours display in Future Scheduled Hours on the Schedule Detail page.

To calculating future scheduled hours immediately:

  1. On the PSA Administration page, click PSA Batch Processes | Calculate Future Time on Schedules. Calculate Future Time on Schedules window opens.
  2. Click Run. The batch job is submitted and the Future Scheduled Hours are calculated.

To schedule a batch job to calculate future scheduled hours:

  1. On the PSA Administration page, click PSA Batch Processes | Calculate Future Time on Schedules. Calculate Future Time on Schedules window opens.
  2. Click Schedule.
  3. Set the schedule day, time, and frequency.
  4. [Optional] To change your selection, click Back.
  5. Click Schedule.
Note:

If your organization has more than 100,000 schedules, your administrator should create new indexes for the End Date and Future Scheduled Hours fields on the Schedule object. The new indexes must be separate, not a compound index.