Using Work Planners

Work planners enable you to plan project work easily by viewing:

  • Assignments and resource requests (you can use the options in the toolbar to group the assignments and resource requests, for example by project or by resource).
  • Resource details and scheduled work.
  • Resource allocations.
  • Company holidays.

The work planners available are tailored to your job role so that you can view and manage the information that is relevant to you.

The Work Planner page is designed for use by resource managers. The data fills the entire page, making it easier to view a large number of projects, assignments, and resource requests. To view the page, do one of the following:

  • Select Work Planner from the App Launcher.
  • Navigate to the customized Work Planner page created by your administrator, if available.

Work planners for other roles are made available by your administrator:

  • Line Manager Work Planner
  • Project Manager Work Planner: this work planner is also part of the Project Management workspace
  • Resource Work Planner
  • Work Planner in Experience Cloud sites

For more information, see Setting up Work Planners, Setting up the Work Planner for PSA Experience Cloud Sites, or contact your administrator.

The work planners contain the following views:

  • Scheduler: Shows assignments and resource requests grouped by project, resource, or RPGClosed Abbreviation of region, practice, group. over time. The default date range is starting 7 days earlier and ending 28 days later from today, or you can specify your own date range in the Filters panel. The scheduler gives a good overview of what a resource is due to work on at a particular time. You can quickly reschedule the assignments and resource requests by dragging them forward or backward to change their start and end dates. For more information, see Changing the Dates of Assignments and Resource Requests.
  • Allocation: Shows assignments and resource requests by project, resource, or RPGClosed Abbreviation of region, practice, group. over the default date range or the date range specified in the Filters panel. Also shows the number of scheduled hours a resource is due to work on the corresponding assignment or resource request and indicates if a resource is allocated within the planned allocation range, under allocated, or over allocated. You can update the scheduled hours displayed to make sure resources carry out the right amount of work at the right time. For more information, see Updating the Hours a Resource is Scheduled to Work and Determining Resource Allocation.

Filtered resources that do not have any assignments or held resource requests are displayed in these views without schedules or hours,

Tips:
  • You can use filters to reduce the amount of data displayed and focus on what you want to view. For more information, see Filtering the Data.
  • To reduce the amount of data displayed in work planners, assignment and resource request records with Exclude from Planners selected are not displayed.
  • The maximum number of resources displayed is 2000, including empty resources and the resources on assignments and resource requests.

For all the lookup fields, you can also click Show All Results for “ ”. The search lookup window opens with the searched string populated in the Search field and displays all related items in the grid.

Select the item from the grid that you want and click Select. The selected item is then displayed in the lookup field. For more information, see Using Advanced Lookup.

Note:

If Shield Platform Encryption is enabled in your org, the records in the Resource, Account, and Opportunity search lookup window are filtered using only the Name field in the grid.

Icons and Color Coding

The following color coding is used on the bars in the scheduler view:

  • Green: Project.
  • Orange: Unheld resource request.
  • Orange border filled with orange: Draft assignment, draft held resource request.
  • Blue border filled with white: Held resource request.
  • Blue border filled with blue: Assignment.
  • Gray border filled with white: When grouping by RPG, this is displayed in the top row of each group to make it easier for you to identify the parent RPG of the records you are viewing.

On the grid view:

  • Cells shaded gray indicate a resource's non-working time and holidays, using the resource's associated work calendar.
  • Over allocated indicates that the resource is over allocated within the time period.
  • Correctly allocated indicates that the resource is scheduled to work the planned number of hours in the time period.
  • Under allocated indicates that the resource is under allocated within the time period.
  • Indicates a billable project or assignment in the Name column.
  • Indicates a non-billable project or assignment in the Name column.
  • Company holiday indicates a company holiday. The color of this icon changes to match the allocation status for various groupings and zoom levels.
  • Italics indicate resource request values that were calculated using a schedule PSA has generated. This happens when resource requests contain requested hours but have no schedule specified in the Preferred Schedule field. PSA uses a resource’s work calendar to identify working days for the generated schedule. If there are no working days available or if there is no work calendar, PSA generates a schedule that splits the requested hours equally across the weekdays. If there are no weekdays available, PSA generates a schedule that splits the hours across all days, including weekends.
  • The following icons help you to differentiate between the different records displayed:
    • Assignment record Assignment
    • Unheld resource request record Unheld resource request
    • Held resource request record Held resource request

For more information, see Updating the Hours a Resource is Scheduled to Work and Determining Resource Allocation.

Switching Views

To switch from one view to another, take the appropriate action:

  • Select Scheduler from the Change View button menu.
  • Select Allocation from the Change View button menu.

You can change the zoom level between Days, Weeks, Months, Quarters, and Years. On the Allocation view, you can only edit the hourly values when using the Days and Weeks zoom levels.

Viewing Record Details

To view the details of an assignment, project, resource, or resource request without leaving the work planner, double-click the record on the Allocation or Scheduler view. The details are displayed in the Record Details panel.

Alternatively, you can:

  1. Select the assignment, project, resource, or resource request on the Allocation or Scheduler view.
  2. Click Record Details.

To view details of any records that are related to the currently selected record, you can switch between the tabs on the Resource Details panel. For example, if you are viewing the details of a held resource request, you can easily switch to the Resource and Project tabs to view details of the related resource and project records.

To hide the Record Details panel, click Close on the panel or click Record Details again.

For more information, see Viewing Record Details.

Grouping Assignments and Resource Requests

To group assignments and resource requests on a work planner, select the appropriate grouping option from the toolbar:

  • Resource
  • Project
  • Region
  • Practice
  • Group

When grouping assignment and resource request records by region, practice, or group, PSA uses the following criteria in the order shown to determine an assignment or resource request record’s RPGClosed Abbreviation of region, practice, group.:

  1. The RPG set on the relevant resource.
  2. The RPG set on the resource request, for resource request records.
  3. The RPG set on the associated project.

If there is no RPG set on any of the above, the record is placed in a grouping called No Region, No Practice, or No Group, as appropriate.

In the top row of each RPG group in the scheduler, a white box with a gray border is displayed to make it easier for you to identify the parent RPG of the records you are viewing.

When grouping resource requests by Resource or Project, if there is no resource or project set on the resource request, the record is placed in a grouping called No Resource or No Project, as appropriate.

Filtering the Data

You can use the Filters panel to reduce the amount of content displayed. Depending on the work planner you are using, the Filters panel defaults to the following:

  • Line Manager Work Planner:
    • The resource associated with your Salesforce user.
    • The resources with your name in the Reports To field on their contact record.
  • Project Manager Work Planner:
    • Any projects where the current user is set as the project manager.
    • Any projects the current user is assigned to.
    • Any projects where the current user is a held resource.
  • Resource Work Planner: The resource associated with your Salesforce user.
  • Work Planner page for resource managers: No default filters. You must open the Filters panel to select and apply filters to display any data.

The details of the filters you have used are displayed in the work planner toolbar.

To filter the content:

  1. Click Filter to open the Filters panel. The filters you last used are retained if you are using the same browser on the same device.
  2. In the General Filters section:
    1. Specify the date range you want to filter by. The default date range is starting 7 days earlier and ending 28 days later from today. You must enter a date range that is less than 365 days if you are using utilization targets.
    2. [Optional] Select Hide Zero Hour Commitments if you do not want to display assignments or resource requests containing zero hours.
    3. [Optional] Select Exclude Assignments if you do not want to display assignments.
    4. [Optional] Select Exclude Unheld Resource Requests if you do not want to display unheld resource requests.
    5. [Optional] Select Exclude Held Resource Requests if you do not want to display held resource requests.
  3. [Optional] In the Filter by Resource section:
    1. Search for and select the resources you want to include in the work planner.
    2. Search for and select the regions, practices, or groups for the resources.
    3. To filter resources by skills and certifications in the Skills section, click Edit Skill Filters. For more information, see Filtering a List of Resources by Skills and Certifications.
  4. [Optional] In the Filter by Project section:
    1. Search for and select the additional projects you want to include.
    2. Search for and select the regions, practices, or groups you want to include.
    3. In the Is Billable field drop-down, select the required preference to display billable or non-billable projects.
  5. [Optional] In the Filter by Assignment section:
    1. Search for and select the additional assignments you want to include.
    2. In the Is Billable field drop-down, select the required preference to display billable or non-billable assignments.
  6. [Optional] In the Filter by Resource Request section:
    1. Search for and select the regions, practices, or groups you want to include.
    2. Search for and select the opportunities to display the related resource requests.
  1. Click Apply. The content displayed reflects the selected filters.
  2. [Optional] Click Reset to reset the Filters panel to its default values.
  3. [Optional] Click Filter to close the Filters panel.
Notes:
  • By default, the Include Sub-Regions, Include Sub-Practices, and Include Sub-Groups checkbox is selected for the Region, Practice, and Group respectively. You can deselect the checkboxes if you want to avoid filtering the resources using sub-levels.
  • The Include Sub-Regions, Include Sub-Practices, and Include Sub-Groups preferences are saved for the next time you open the work planner.
  • If there are too many assignments and resource requests to show, a message is displayed so you can change the filters to reduce the number of records returned. Records are displayed in start date order, which means any records that cannot be shown are missing from the foot of the Allocation view.

For details of the criteria PSA uses to determine an assignment or resource request record’s RPG, see Grouping Assignments and Resource Requests.

You can use these filter sections in combination to find the required results in a work planner:

  • To see the unheld resource requests use a combination of filters in the General Filters, Filter by Resource Request, and Filter by Project.
  • To see the held resource requests use a combination of filters in the General Filters, Filter by Resource Request, Filter by Resource, and Filter by Project.
  • To see assignments use a combination of filters in the General Filters, Filter by Assignment, Filter by Resource, and Filter by Project.
Tips:
  • An administrator can override the fields displayed in the filter sections using field sets in the Lightning App Builder. For more information, see Work Planner Lightning Component Properties.
  • The sub-level filtering option is also included in the custom RPG fields added to the field sets to override the default RPG fields in the Filter by Resource Request, Filter by Resource, and Filter by Project sections.
  • Field types that are not supported in work planner filters: date/time, phone, email, text area, text area long, text area rich, time, encrypted, and multi-picklist.
  • The fields in the General Filters are not configurable.
  • The field sets for Filter by Resource, Filter by Assignment, Filter by Project, and Filter by Resource Request sections can override the default fields in those sections.
  • If the field sets overriding the fields in the Filter by Assignment and Filter by Project sections contain the Start Date and End Date fields, then the Start Date and End Date fields will not be displayed as they are already included in the General Filters.
  • When overriding the fields in the Filter by Resource section, if the field sets contain the Start Date and Last Date fields, then those fields are not visible as they are already included in the General Filters.
  • Similarly, when overriding the fields in the Filter by Resource Request section, if the field sets contain the Start Date, End Date, and Resource Held fields, then those fields are not visible as they are already included in the General Filters.
  • An administrator must assign you the PSA - View Work Planner permission set and Skill or Certification Rating object read permission to use the Skills in the Filter by Resource section.
  • After overriding the fields in the Filter by Resource section, the Skills section is not displayed.
  • The resource and project name fields will always be visible in their respective Filter by Resource and Filter by Project sections only, even when they are used for overriding fields in other filter sections.

Saving your Filters

You can save your filter selection by assigning them a unique name. By saving your filter selection, you can quickly apply the same set of filters without manually configuring them each time you open the Filters panel.

To save your filters:

  1. Click Filter to open the Filters panel.
  2. Select the filters you want to save.
  3. Click Down arrow | Save As. The Save Filter window opens.
  4. In the Filter Name field, enter a unique name for your filter.
  5. [Optional] Select the Save as Default checkbox if you want to save it as your default filter.
  6. Click Save. The filters are saved in the Saved Filters drop-down list.
  7. [Optional] Click Reset to clear all the filters applied in the Filters panel.
Notes:
  • When using field sets to add or remove fields displayed in the filter sections for saved filters, an error might be displayed for outdated values.
  • The state of saved and default filter sets fields is maintained, when using field sets in the Lightning App Builder.
  • If a filter set contains a field value that does not exist on the user interface (UI), that filter set is considered invalid.
  • The work planner is always filtered by the locally saved, last-applied filters until you choose to save a filter as default. However, the locally saved last applied filters will be retained, if you are using the same browser on the same computer.
  • Once you save a filter as default, regardless of refreshing or reloading the work planner, you will consistently view the data filtered by the default filter that you have applied.

 

Using Filter Set Controls

To access the filter set controls, click . The following options are available:

  • Set as Default: Select this option to set the selected filter from the Saved Filters drop-down list as your default filter.
  • Remove Default: This option is only available if the filter currently selected in the Saved Filters drop-down list is your default filter. Select this option if you want to remove the default setting from the selected filter.
  • Edit: Select this option to edit the selected filter. To edit the saved filter:
    1. Select Edit. The Edit Filter window opens.
    2. [Optional] In the Filter Name field, enter the name of the filter you want to rename it to.
    3. [Optional] Select or deselect the Save as Default checkbox according to your preferences.
  • Delete: Select this option to delete the selected filter from the list of Saved Filters.
Note:

You can save up to 50 filters in the Saved Filters list.

Updating the Hours a Resource is Scheduled to Work

Note:

To update values on the Allocation view, your administrator must have assigned you the PSA - Edit Work Planner permission set.

To update the number of hours a resource is scheduled to work:

  1. Select Grid from the Change View button menu and check the zoom level is set to Days or Weeks.
  2. Navigate to the relevant date. If the date you want is not displayed, select and apply the appropriate date range using the Filters panel. For more information, see Filtering the Data.
  3. Double-click the value you want to change. For information on the icons displayed, see Icons and Color Coding.
  4. Type the new value and press Enter. Above the grid, Unsaved Changes is displayed to indicate that you must save when you have finished your updates.
  5. [Optional] Repeat Steps 3 and 4 to update other values in the grid.
  6. Click Save.

If you add or update an hourly value from the Weeks zoom level, PSA applies the following rules:

  • If the relevant resource has an associated work calendar, the value is split equally across all working days in the given week.
  • If the relevant resource has an associated work calendar but there are no working days in the given week, the value is split equally across Monday to Friday.
  • If the relevant resource has no associated work calendar, the value is split equally across Monday to Friday.

You cannot edit hourly values displayed in italics. Italics indicate resource request values that are calculated using a schedule generated by PSA because the resource request does not have a schedule specified in the Preferred Schedule field.

For more information on values displayed in italics, see Icons and Color Coding.

The total number of hours for each group of projects or resources is displayed in the top row of each group in the grid. The total number of hours on the schedule for the associated assignment or resource request is displayed in the Total Hrs column. This value reflects the total scheduled hours for the associated assignment or resource request across the entire schedule, not just the days specified in the filter criteria.

Tips:

To extend the start or end date of a resource’s schedule, update the hours outside the scheduled date range.

To expand or collapse a row in the grid, press Enter.

To move forward through the cells in the grid using your keyboard, press Tab. To move backward, press Shift + Tab. If you are using Apple Safari, ensure that you have "Press Tab to highlight each item on a webpage" enabled in your browser settings.

If you update a value and then change your mind before clicking Save:

  • If you have not moved away from the cell, press Escape to restore the original value.
  • If you have moved away from the cell or changed more than one value, click Reload to return to the last saved state.

Creating Assignments

To create an assignment from the Allocation or Scheduler view:

Note:

To create assignments you must have the PSA - Edit Work Planner permission set and the Staffing permission control assigned. For more information, contact your administrator.

  1. Click Create Assignment. The Create Assignment window opens.
  2. In the Select Project field, select a project and click Next. Only active projects that have Staffing permission control assigned are available for selection.
  3. Complete the fields to create an assignment. Only active resources are available for selection. For more information, see Assignment Information and Schedule Details.
  1. Click Create. A draft assignment is created.
  2. [Optional] Drag the cloned draft assignment to a new start date on the scheduler to reschedule it.
  3. Click Save on the Work Planner to save the draft assignment.
  4. [Optional] If you have moved away from a cell or changed more than one value, click Reload to return to the last saved state. The Unsaved Changes window opens.
  5. Click Continue Editing, Discard and Continue, or Save and Continue as required.
Tips:
Check Setup | Apex Jobs after saving a draft assignment or click Reload button to update the new schedule.
An administrator can use the Assign Resource To Project Custom Fields field set on the Assignment object to customize the fields displayed in the Create Assignment window. For more information, see Work Planner Lightning Component Properties.
Notes:
  • The draft assignment is not visible in a work planner when the selected resource or project is not available on the Allocation or Scheduler views.
  • If there is an existing draft assignment for a resource and you try to create another for the same resource using the Calculate End Date, Level Schedule scheduling strategy with either the start date or end date falling between the same date range as the existing one, it means the two draft assignments overlap. It is recommended that you either change the selected scheduling strategy or change the draft assignment start date or end date so it does not fall between the same date range.

Cloning Assignments

Note:

To clone assignments you must have the PSA - Edit Work Planner permission set and the Staffing permission control assigned. For more information, contact your administrator.

To clone an assignment from the Allocation or Scheduler view:

  1. Right-click the assignment and select Clone Assignment. The Clone Assignment window opens, displaying the name of the assignment to be cloned and the current resource in the Assignment Details section.
  2. In the New Resource for Cloned Assignment section, do the following:
    1. [Optional] Filter the resources using the Filter by Resource Role field. The resource role is not required for cloning assignments and is made available for filter purposes only.
    2. Enter the first few words of the resource name and select a resource for the new draft assignment. The resources with Staffing permission control assigned are available for selection.
    3. When the filter is applied, the resources filtered by that role with staffing permission are displayed.

  3. [Optional] In the Edit Assignment Name section, enter a name for the new assignment in the Assignment Name field. If you don't enter an assignment name, the new assignment name defaults to the project name - the new resource name.
  1. Click Clone. A draft assignment is created.
  2. [Optional] Drag the draft assignment to a new start date on the scheduler to reschedule it.
  3. Click Save on the Work Planner to save the draft assignment.
  4. [Optional] If you have moved away from a cell or changed more than one value, click Reload to return to the last saved state. The Unsaved Changes window opens.
  5. Click Continue Editing, Discard and Continue, or Save and Continue as required.
Note:
The draft assignment is not visible in the work planner when the selected resource is unavailable on the Allocation or Scheduler view.

Creating Resource Requests

To create a resource request from the Allocation or Scheduler view:

Note:

To create resource requests, you must have the following:

  • PSA - Edit Work Planner permission set
  • Either the Resource Request Entry permission control assigned for the Region, Practice, or Group or a Salesforce User defined on the Contact.

For more information, contact your administrator.

  1. Click Create Resource Request. The Create Resource Request window opens.
  2. Complete the fields in the Information section. For more information, see Resource Request Details Fields.
  3. In the Skills Selection section, select the skill, certification, or skill set. By default, Skill or Certification is selected in the picklist.
  4. Click the lookup to search and select the skill, certification, or skill set to add.
  5. [Optional] Click Show All Results for " ". The Select Skill or Certification window opens with the searched string in the Search field, and all the related items are displayed in the grid.
  6. [Optional] Select the skill, certification, or skill set from the grid and click Select.
  7. Click Edit to edit the Minimum Rating field.
  8. Click Create. A draft resource request is created.
  9. [Optional] Drag the draft resource request to a new start date on the scheduler to reschedule it.
  10. Click Save on the Work Planner to save the draft resource request.
  11. [Optional] Double-click the saved resource request to open the Record Details panel.
  12. [Optional] If you have moved away from a cell or changed more than one value, click Reload to return to the last saved state. The Unsaved Changes window opens.
  13. Click Continue Editing, Discard and Continue, or Save and Continue as required.
Tip:

An administrator can use the Create Resource Request Custom Fields field set to customize the fields displayed in the Create Resource Request window. For more information, see Work Planner Lightning Component Properties.

Notes:
  • The created resource requests will always be unheld with no resource held.
  • Double-clicking a draft resource request will not open the Record Details panel.
  • If you open the Record Details panel by double-clicking a saved resource request and then select a draft resource request while the panel is still open, only project details are shown in the Record Details panel for the draft resource request.
  • The resource requests that are created against an opportunity and do not have any project associated are grouped under No Project.
  • To view the Skills Selection section, you must have the Skill or Certification Rating object permission assigned. For more information, contact your administrator.

Cloning Resource Requests

To clone a resource request from the Allocation or Scheduler view:

Note:

To clone resource requests, you must have the following:

  • PSA - Edit Work Planner permission set.
  • Either the Resource Request Entry permission control assigned for the Region, Practice, or Group or a Salesforce User defined on the Contact.

For more information, contact your administrator.

  1. Right-click the resource request and select Clone Resource Request. The Clone Resource Request window opens displaying the details of the selected resource request in the Resource Request Details section.
  2. Complete the fields in the Resource Request Details section. For more information, see Resource Request Details Fields.
  3. Click Clone. A draft resource request is created.
  4. [Optional] In the Clone Requested Skills section, select the checkbox if you want to clone all the Requested Skills for this resource request.
  5. [Optional] Drag the draft resource request to a new start date on the scheduler to reschedule it.
  6. Click Save on the Work Planner to save the draft resource request.
  7. [Optional] Double-click the saved resource request to open the Record Details panel.
Tip:

An administrator can use the Clone Resource Request Custom Fields field set to customize the fields displayed in the Clone Resource Request window. For more information, see Work Planner Lightning Component Properties.

 

Notes:
  • Cloned resource requests are always unheld even when they are cloned from held resource requests.
  • Double-clicking a draft resource request does not open the Record Details panel.
  • If you open the Record Details panel by double-clicking a saved resource request and then select a draft resource request while the panel is still open, only project details are shown in the Record Details panel for the draft resource request.
  • Resource requests that are cloned against an opportunity and do not have any project associated are grouped under No Project.

Swap Resource and Split Assignment

To swap a resource or split an assignment you must have the PSA - Edit Work Planner permission set and the Staffing permission control assigned. For more information, contact your administrator.

To swap a resource or split an assignment from the Allocation or Scheduler view:

  1. Right-click an assignment and select Swap Resource & Split Assignment. The Swap Resource & Split Assignment window opens, displaying the selected assignment's details in the Current Information section.
  2. In the Select an Option section, do one of the following:
    1. Select Swap Resource to swap the existing resource with a new one and perform the following steps:
      1. [Optional] Filter the resources using the Filter by Resource Role field.
      2. In the Resource Name lookup field, enter the first few words of the resource name and select an active resource for the resource request. The Region field auto populates.
    2. Select Split Assignment and perform the following steps:
      1. [Optional] Filter the resources using the Filter by Resource Role field.
      2. In the Resource Name lookup field, enter the first few words of the resource name and select an active resource for the new resource request. The Region field auto populates.
      3. In the Start Date of Split field, enter a valid date to split the assignment. The date must be between the start and end date range of that assignment.
  3. Click Apply.
  4. [Optional] Drag the draft assignment to a new start date on the scheduler to reschedule it.
  5. Click Save on the Work Planner to save the draft assignment.
  6. [Optional] If you have moved away from a cell or changed more than one value, click Reload to return to the last saved state. The Unsaved Changes window opens.
  7. Click Continue Editing, Discard and Continue, or Save and Continue as required.
Note:

You cannot split assignments or swap resources for assignments associated with timecards or expenses.

Swap Resource and Split Resource Request

To swap a resource or split a resource request you must have the PSA - Edit Work Planner permission set assigned. Also, to split a resource request you must have the Resource Request Entry permission assigned. For more information, contact your administrator.

To swap a resource or split a resource request from the Allocation or Scheduler view:

  1. Right-click a resource request and select Swap Resource & Split Resource Request. The Swap Resource & Split Resource Request window opens, displaying the selected resource request's details in the Current Information section.
  2. In the Select an Option section, do one of the following:
    1. Select Swap Resource, to swap the existing resource with a new one.
      1. [Optional] Filter the resources using the Filter by Resource Role field.
      2. In the Resource Name lookup field, enter the first few words of the resource name and select an active resource for the resource request. The Region field auto populates.
    2. Select Split Resource Request and perform the following steps:
      1. [Optional] Filter the resources using the Filter by Resource Role field.
      2. In the Resource Name lookup field, enter the first few words of the resource name and select an active resource for the new resource request. The Region field auto populates.
      3. In the Start Date of Split field, enter a valid date to split the resource request schedule. The date must be between the start and end date range of that resource request schedule.
  3. Click Apply.
  4. [Optional] Drag the draft resource request to a new start date on the scheduler to reschedule it.
  5. Click Save on the Work Planner to save the draft resource request.
  6. [Optional] If you have moved away from a cell or changed more than one value, click Reload to return to the last saved state. The Unsaved Changes window opens.
  7. Click Continue Editing, Discard and Continue, or Save and Continue as required.
Note:

You cannot split or swap resource on unheld resource requests.

Changing the Dates of Assignments and Resource Requests

Note:

To update assignments and resource requests on the scheduler view, your administrator must have assigned you the PSA - Edit Work Planner permission set.

To update the dates of assignments or resource requests from a work planner:

  1. Select Scheduler from the Change View button menu.
  2. Drag the resource request or assignment to a new start date. Although schedules are preserved where possible, the end date might be recalculated to take account of non-working days.
  3. Click Save.
  4. [Optional] Hover over the assignment or resource request to view the updated start and end dates.
Tip:

If you drag an assignment or resource request and then change your mind, click The Reload button. to return to the last saved state.

Determining Resource Allocation

PSA uses a resource's associated work calendar to determine whether the resource is scheduled to work the right number of hours. For more information on work calendars, see About Time Periods, Work Calendars, and Holidays.

The following coloring and graphics are displayed in the Allocation view when grouping by resource:

  • If a resource has zero hours on their work calendar for a particular period of time (for example, day or week), the relevant cell is shaded in gray to indicate non-working time or a holiday.
  • Over allocated is displayed in the cell next to the value if a resource is over allocated.
  • If the total value exceeds a resource's work calendar hours for the corresponding period of time (for example, day or week) taking holidays into account, the following icons are displayed in the cell containing the summary value:
    • Over allocated indicates that the corresponding resource is over allocated.
    • Correctly allocated indicates that the corresponding resource is scheduled to work the planned number of hours.
    • Under allocated indicates that the corresponding resource is under allocated.

    If there is a holiday within a cell's time period, the company holiday icon changes color to reflect these allocation statuses.

Note:

Correctly allocated and Under allocated are displayed next to the summary value only and not in the cells that correspond to individual assignments or resource requests. That is because the relevant resource might be scheduled to work on more than one assignment or resource request during the corresponding period of time (for example, day or week).

If you have the required permissions, you can:

Setting Display Preferences

The Preferences panel relates to the Allocation view, and enables you to:

  • Set the limits for the display of resource allocation statuses.
  • Show the resource allocation statuses using cell colors or icons.
  • Change the colors of the cell or icons to show resource allocation statuses.
  • Use each resource's utilization target and the allocation values to calculate the allocation colors.

To open the Preferences panel and set the display preferences:

  1. Click Preferences panel button..
  2. In the Less Than and Greater Than fields, enter the percentage values that you want to use to calculate the resource work allocations. The Planned Allocation Range is populated with your values to indicate the range for the optimal allocation.
  3. [Optional] Select the Use Cell Shading checkbox to color the grid cells instead of using the graphics to indicate each resource's allocation status.
  4. [Optional] Select the Show Totals as Percentages checkbox to show the top-level totals for resources in the Allocation view as percentages.

    If the Use Utilization Target checkbox is also selected, the percentages are calculated relative to the utilization target value. For more information, see Allocation Thresholds Including the Utilization Target

  5. [Optional] Select the Use Utilization Target checkbox to use the resource's utilization target in the calculation. For more information, see Allocation Thresholds Including the Utilization Target.

If the resource's allocation is below the Less Than value, the resource is under allocated for that day, week, month, and so on. If the resource's allocation is above the Greater Than value, the resource is over allocated.

The calculation for the allocation thresholds is:

Work calendar hours * Planned allocation (Less Than or Greater Than value) = Allocation threshold

Example: Example for weekly hours:
  • A resource's weekly work calendar hours = 40
  • Less Than value = 50%
  • Greater Than value = 80%

The calculation uses decimal values, so for these values the calculations are:

  • Under allocated: 40 * 0.50 = 20 hours
  • Over allocated: 40 * 0.80 = 32 hours

Therefore, the planned allocation for these resources is 20 to 32 hours per week, and the relevant graphics and colors are applied in the Allocation view to indicate the under allocation, planned allocation range, and over allocation of resources.

Allocation Thresholds Including the Utilization Target

When you select the Utilization Target checkbox, each resource's utilization target is used with the allocation percentages to calculate the resource's allocation status.

The utilization target is set on the Contact object for each resource and is a percentage of the resource's weekly work calendar hours. When this utilization target is used, the Less Than and Greater Than percentages are relative to the utilization target percentage when calculating the resource's hours.

The calculation for the allocation thresholds using the utilization target is:

Work calendar hours * Utilization target * Planned allocation (Less Than or Greater Than value) = Allocation threshold

Example: For weekly hours:
  • A resource's weekly work calendar hours = 40
  • A resource's utilization target = 75% (30 hours)
  • Less Than value = 50%
  • Greater Than value = 80%

The calculation uses decimal values, so for these values the calculations are:

  • Under allocated: 40 * 0.75 * 0.50 = 15
  • Over allocated: 40 8 0.75 * 0.80 = 24

Therefore, the planned allocation for these resources is 15 to 24 hours per week, and the relevant graphics and colors are applied in the Allocation view to indicate the under allocation, planned allocation range, and over allocation of resources.