Splitting Assignments and Held Resource Requests

You can split an individual assignment or held resource request into two assignments or held resource requests. When you split, new assignments and held resource requests are created with new schedules and schedule exceptions.

Note:

You cannot split assignments with associated timecards or expenses.

You cannot split resources on unheld resource requests.

You cannot split assignments or resource requests if you do not have edit permissions through field-level security or create, retrieve, update, delete access.

Your administrator can select Restrict Creation Past Dates to specify whether users can split assignments with a start date set in the past.

To split an Assignment or Resource Request:

  1. In Resource and Project Planners, select an assignment or resource request.
  2. Click Split Assignment.
  3. Enter a valid date to split the assignment or resource request.
  4. From the drop-down list, select an active resource.
  5. Click Split | Save.