Mass Linking Project Task Assignments
PSA enables you to link multiple project task assignments, to a resource request or an assignment, or both.
To link project task assignments:
- On a project record, click Actions | Task-Based Resourcing | Mass Link Project Task Assignments.
- [Optional] Click
to open and close the Filters. Select the filter criteria to filter the project task assignments and click Apply. The project task assignments that meet your criteria are displayed. See Mass Link Project Task Assignment Fields in Lightning for more information.
- Click Clear to remove the applied filters.
- From the Resource Request to Link or Assignment to Link lookups, select the resource request or assignment, or both that you want to link the assignments to.
- The Resource, Role, Start Date and End Date in the read only fields and filters are automatically populated with the details of the resource request or the assignment selected from the lookups.
For all the lookup fields, you can also click Show All Results for “ ”. The search lookup window opens with the searched string populated in the Search field and displays all related items in the grid.
Select the item from the grid that you want and click Select. The selected item is then displayed in the lookup field. For more information, see Using Advanced Lookup.
- Select the project task assignments you want to link.
- Click Link Project Task Assignments.