Dated Resource Rates Overview
Dated resource rates enable the bill or cost rate used by a resource request or assignment to continuously update in sync with changes to rates on the linked bill rate card or cost rate card. For example, if an assignment spans multiple years and a new bill or cost rate is introduced during the second year, the assignment will automatically start using the new rate from the date it becomes effective. This means that the initial rate applied to an assignment can change within its duration.
Dated Resource Bill Rate Example
When a timecard is submitted for an assignment that uses dated resource bill rates, the bill rate in effect on each day of the timecard is used. For example, the rate card linked to a long-running assignment has the following dated resource bill rates:
| Effective Date | Rate |
|---|---|
| January 1, 2024 | 100 |
| January 1, 2025 | 150 |
Assuming that the bill rate is a daily rate, when the resource working on that assignment submits timecards for 2024 their daily bill rate is 100, and for 2025 their daily bill rate is 150. For the week commencing December 30, 2024, the following bill rates apply:
| Day | Bill Rate |
|---|---|
| Monday, December 30 2024 | 100 |
| Tuesday, December 31 2024 | 100 |
| Wednesday, January 1 2025 | 150 |
| Thursday, January 2 2025 | 150 |
| Friday, January 3 2025 | 150 |
The total billable amount for the timecard split that covers Monday - Tuesday is 2 x 100 = 200.
The total billable amount for the timecard split that covers Wednesday - Friday is 3 x 150 = 450.
The total billable amount on the timecard header is 200 + 450 = 650. The bill rate on the timecard header is an average: 650 / 5 = 130.
Dated Resource Cost Rate Example
When a timecard is submitted for an assignment that uses dated resource cost rates, the cost rate in effect on each day of the timecard is used. For example, the rate card linked to a long-running assignment has the following dated resource cost rates:
| Effective Date | Rate |
|---|---|
| January 1, 2025 | 60 |
| January 1, 2026 | 80 |
Assuming that the cost rate is a daily rate, when the resource working on that assignment submits timecards for 2025 their daily cost rate is 60, and for 2026 their daily cost rate is 80. For the week commencing December 29, 2025, the following cost rates apply:
| Day | Cost Rate |
|---|---|
| Monday, December 29 2025 | 60 |
| Tuesday, December 30 2025 | 60 |
| Wednesday, December 31 2025 | 60 |
| Thursday, January 1 2026 | 80 |
| Friday, January 2 2026 | 80 |
The total cost amount for the timecard split that covers Monday - Wednesday is 3 x 60 = 180.
The total cost amount for the timecard split that covers Thursday - Friday is 2 x 80 = 160.
The total cost amount on the timecard header is 180 + 160 = 340. The cost rate on the timecard header is an average: 340 / 5 = 68.
For information about creating rate cards with dated resource rates, see Creating Rate Cards.
Using Dated Resource Rates
To use dated resource bill rates with a resource request or assignment, you must select the Use Dated Resource Bill Rates checkbox when creating the record. If you create an assignment from a resource request, the assignment's Use Dated Resource Bill Rates checkbox defaults from the resource request. On saving the resource request or assignment, its Bill Rate Card field is populated automatically with a rate card that matches the relevant criteria. For more information about how rate cards are matched automatically, see Rate Card Matching When Using Dated Resource Rates.
To use dated resource cost rates with a resource request or assignment, you must select the Use Dated Resource Cost Rates checkbox when creating the record. If you create an assignment from a resource request, the assignment's Use Dated Resource Cost Rates checkbox defaults from the resource request. On saving the resource request or assignment, its Cost Rate Card field is populated automatically with a rate card that matches the relevant criteria.
Once a bill rate card or cost rate card is matched to a resource request or assignment, its dated resource rates are used as follows:
- Dated resource bill rates are used to calculate the Request Billable Amount on resource requests. For more information about how this amount is calculated, seeCalculating a Resource Request's Billable Amount When Dated Rates Are Used.
- Dated resource cost rates are used to calculate the Projected Cost Amount on resource requests. For more information about how this amount is calculated, seeCalculating a Resource Request's Projected Cost Amount When Dated Rates Are Used.
- Dated resource bill rates are used to calculate the EVA scheduled amounts, projected revenue, and planned revenue on assignments. They also populate the bill rates per day on timecards linked to the assignment, which are used to calculate the assignment's EVA actual amounts. For more information about scheduled and actual value calculations, seeEVA Calculations when Dated Resource Bill Rates Apply to Assignments and Timecards. For more information about projected and planned revenue, seeAssignment Fields. For more information about EVAs, seeEstimates Versus Actuals.
- Dated resource cost rates are used to calculate the Projected Cost Amount on assignments, and populate the cost rates per day on timecards linked to the assignment.
For an overview of where dated resource bill and cost rates are used in Professional Services Cloud, see Understanding Where Dated Resource Rates Are Used in Professional Services Cloud.