Adjust Hours Strategy Respects Holidays |
Indicates whether the scheduling strategy respects work calendar holidays and sets hours to zero for zero hour holidays. When selected:- Hours are spread across other days and a schedule exception is created.
- No schedule exception is generated when a non-working holiday occurs during a weekend.
- A schedule exception is created for working holidays that occur during a weekday or a weekend. The exception hours are equal to the adjusted hours per day or equal to the holiday hour.
|
|
Adjust Sched Date on Assignment Close |
Indicates whether the end date of an assignment is automatically set to today's date when a closed status is detected and the schedule end date is past today's date.
|
|
Assignment Closed Statuses |
A comma-delimited list of assignment status values that dictate when an assignment is closed. |
|
Assignment Name Project Name Max Length |
Maximum number of characters from the project name in an automatically generated Assignment Name. |
|
Assignment Name Resource Name Max Length |
Maximum number of characters from the resource name in an automatically generated Assignment Name. |
|
Assign Resource Custom Lookup |
Indicates whether the a custom resource lookup popup is displayed in place of the standard resource lookup when assigning a resource. |
|
Assign Resource Custom Lookup Columns |
API names of the columns to display on the Assign Resource Custom lookup |
|
AssigRes IsResource Active Lookup FIlter |
Indicates whether the resource lookup filters out inactive resources when assigning resources to projects. |
|
AssigRes Is Resource Lookup Filter |
Indicates whether the resource lookup filters out contacts that are not resources when assigning resources to projects. |
|
Display Planned Bill Rate |
Indicates whether the Planned Bill Rate Appears on the Mass Assign Projects to Resource, Resource Request and Assignment pages. |
|
Edit Schedule Default Strategy |
The default scheduling strategy for the Schedule Strategy field on the Edit Assignment Schedule page. You can set this to one of the following:
- "level" for Calculate End Date, Level Schedule.
- "ignore" for Calculate End Date, Ignore Availability.
- "day" for Adjust Hours Per Day.
|
|
Role Required on Creation |
Indicates whether the Role field is mandatory when creating a new assignment on the Assign Resource to Project, Assign Multiple Resources to Project and Mass Assign Resources to Project pages. |
|
Timecard Statuses |
The comma-delimited list of the Timecard Status field values to use when performing timecard calculations for the Edit Assignment Schedule page. |