Task Management Enhanced Fields

Here is a description of the fields and buttons on the enhanced task management user interface.

Task List

Field Description
Show: Displays the project tasks for the selected project.
Checkbox Indicates whether the task is selected. When you carry out an action such as assigning users to tasks, the action is applied to the selected tasks.

Task List Buttons

Button Description
Add Task Adds a new project task.
Add Task Add a new task line beneath the last selected task where you can enter details for a new task. If you do not enter a task name, the new task is not saved.
Assign To Allows you to assign resources to the selected tasks and remove assignments.
Back to Project Closes the enhanced task management user interface and returns the browser to the project on the main PSA user interface.
Block/Unblock buttons Marks the selected tasks as Blocked or Unblocked.
Dependent Upon Displays a popup where you can make the selected tasks dependent upon another task. When you do this, these tasks start after their predecessor.
Edit Allows you to edit the details of a task.
Expand All/Collapse All Buttons Expands or collapses the task hierarchy shown.
Left/Right Arrow Buttons Changes the parent of the selected task. When you make changes to the hierarchy, the Start and End dates of related tasks such as parent tasks are updated to reflect the changes.
Refresh Tasks Refreshes the displayed tasks
Up/Down Arrow Buttons Changes the order of the selected task.When you make changes to the hierarchy, the Start and End dates of related tasks such as parent tasks are updated to reflect the changes.

Task Details

Key: 255 or 32k – maximum field length.

Field   Description
Actual End Date & Time   Date and time on which the task actually completed. This is the date on which the Completed checkbox was selected.
Actual Start Date & Time   Date and time on which the task actually started. This is the date on which the Started checkbox was selected.
Blocked   Indicates whether the task is blocked.
Completed   Indicates whether the task is complete.

Description

255 Description for the project task.
Do Not Auto Update Parents   Indicates whether changes to this task are to be automatically reflected in the parent tasks.
Do Not Auto Update This Task   Indicates whether the task is to be excluded from automatic updates.
End Date   The date and time on which work for this task is projected to end. Timecards can still be entered for a task after this date as long as it is not closed for time entry.
End Date & Time   The date and time on which work for this task is projected to end. Timecards can still be entered for a task after this date as long as it is not closed for time entry.
Long Description 32k Extended description for the project task.
Number of Assignments   Number of resources assigned to the task.
Percent Complete (Points)   The total number of completed project task points divided by total number of project task points related to this one. This includes child tasks. This field updates as the project is completed.
Percent Complete (Tasks)   The total number of completed project tasks divided by total number of project tasks related to this one. This includes child tasks. This field updates as the project is completed.
Points   Points allocated to the task. The burn-down points. For instance, you can assign a complex task a higher number of points than a simpler one. You can also relate points to a time unit, such as hours.
Points Baseline   Points allocated to the task.
Points Complete   The number of project task points that are completed.
Points Remaining   The number of project task points that are yet to be completed.
Priority   The current priority of the selected task.
Project Task Name   The name representing the project task and its children if applicable.
Note
A Project Task’s Name chain field length cannot exceed 255 characters. If you plan to have several levels of child Project Tasks, consider using shorter project task names.
Start Date   The date and time on which work for this task is projected to start. Timecards can still be entered for a task before this date as long as it is not closed for time entry.
Start Date & Time   The date and time on which work for this task is projected to start. Timecards can still be entered for a task before this date as long as it is not closed for time entry.
Started   Indicates whether the task is started.
Status   The status of the project task. the default values are Deferred, In Progress, and Aborted.
Summary   Indicates whether the task is a top-level parent project task. PSA automatically selects the option when this Project Task is designated as a top-level parent project.

Related Information

Task Management Enhanced

Project Tasks

Related Tasks

Managing Project Tasks

Adding a Project Task

Assigning Resources to a Project Task

Deleting Tasks

Editing Project Task Details

Marking Tasks as Blocked or Unblocked

Moving Tasks in the Hierarchy

Viewing Detailed Task Information

© Copyright 2009-2012 FinancialForce.com, inc. All rights reserved.