| Action: Force Reschedule Refresh |
|
If checked when you save, Scheduled Hours, Assignment Projected Revenue, and Est Vs Actuals records related to Schedules and Assignments refresh. |
| Action: Update Future Scheduled Hours |
|
If checked when you save, Future Scheduled Hours refresh. |
| Future Scheduled Hours |
|
The total number of remaining scheduled hours. |
| Future Scheduled Hours Last Updated Date |
|
The last updated date for Future Scheduled Hours calculation. |
| Is Blocking |
|
If selected, this schedule blocks other assignments created with the Team Schedule Planner application.
|
| Monday Hours |
|
Default number of hours to be scheduled on each day. These are used when creating a new resource schedule. |
| Scheduled Days |
R |
The number of scheduled days. |
| Scheduled Hours |
R |
The number of scheduled hours. |
| Week Total Hours |
R |
The total of daily hours. |
| Monday Start Time |
|
The start time for the indicated day. |
| Monday End Time |
|
The end time for the indicated day. |