You can change a preference in the Project Task Gantt Custom Preferences page. When you change a preference, an equivalent mapped custom setting is also updated in Project Task Gantt Settings and Preferences
Updates to custom preferences apply immediately when changed in Project Task Gantt and do not require a refresh, except for:
The Zoom level and Task selection custom preference settings apply to the initial load of Project Task Gantt. Your selected behavior displays in subsequent loading of Project Task Gantt.
To modify custom preferences:
|
Alerts Tab Preference Setting |
Maps To Field |
Custom Setting |
|---|---|---|
| Milestone alerts | Alerts - Task dates - Milestone | Project Task Gantt Preferences. |
| PTA date alerts | Alerts - Task dates - PTA dates | |
| PTA hours alerts | Alerts - Task hours - PTA hours | |
| Project alerts | Alerts - Task dates - Project |
|
Assignments Tab Preference Setting |
Maps To Field |
Custom Setting |
|---|---|---|
| Auto linking assignments | Suppress Auto Link Assignment | Project Task Gantt Preferences. |
|
Display Tab Preference Settings |
Maps To Field |
Custom Setting |
|---|---|---|
| Enable Day Detail | Enable Day Detail | Project Task Gantt Preferences. |
| Save preview dialog | Hide Preview and Confirmation on Save | |
| Zoom level | Zoom Level |
|
Tasks Tab Preference setting |
Maps To Field |
Custom Setting |
|---|---|---|
| Task selection | Single Click Task Selection | Project Task Gantt Preferences. |
| Hours complete percentage | Show Hours Completion % in Task Bar | Project Task Gantt Settings. |
| Show Task Notes | Show Task Notes | |
| Points complete percentage | Show Points Completion % in Task Bar |