How Total Contract Value is Calculated

Total Contract Value (TCV) is the sum of a contract's Total Contract Line Values (TCLV). The Total Contract Line Value (TCLV) of a line is its Sales Price * Number of Terms.

Several factors affect TCV and TCLV calculations:

Note:

The TCV is always calculated based on the current state of the contract. If something changes during the life of a contract that affects its TCV, any amounts that have already been billed are unchanged.

Example

A contract starts on August 1, 2017 and ends on August 31, 2017. It has three lines as shown in the table below.

Billing Type

Sales Price

Start Date

End Date

Billing Term

TCLV without proration

TCLV with Actual Days proration

One-off 100 Aug 1, 2017 Aug 31, 2017   100 100
Recurring Variable - Aug 1, 2017 Aug 31, 2017   - -
Recurring Fixed 70 Aug 12, 2017 Aug 26, 2017 WB + 3d 210 150
             
        TCV 310 250

The TCLV for the One-off contract line is its sales price (100) regardless of whether or not proration applies to the contract.

There is no TCLV for the Recurring Variable contract line because it has no Sales Price and will be billed on usage.

The TCLV of the Recurring Fixed line varies if proration applies to the contract. Without proration, the TCLV is 210 because the line extends across three billing periods (70 * 3 = 210). With proration, the TCLV is the sum of:

charge for partial start period + charge for one whole period + charge for partial end period

As shown in the table above, if the contract's proration policy uses the Actual Days calculation method and the week begins on Monday, the TCLV will be 50 + 70 + 30 = 150 because the partial start period is 5 days, the second period is a whole period of 7 days, and the partial end period is 3 days.

Illustration

Different proration calculation methods will result in different values for the start and end periods. See Proration Policies and Calculating Partial Periods for more information.

Related Concepts

Contracts

Change Requests

Enhanced Contracts Overview

Related Tasks

Activating a Contract

Adding a Plan or Product to a Contract

Billing for Usage

Calculating Contract Values

Creating a Contract

Creating a Contract from a Plan

Deleting a Contract

Editing a Contract

Ending Contracts

Creating Billing Schedules from Contracts

Creating Billing Documents

Reference

Contract Fields

© Copyright 2009-2018 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.