Mass Linking Project Task Assignments
PSA enables you to link multiple project task assignments, to a resource request or an assignment, or both.
To link project task assignments:
- On a project record, click Actions | Task-Based Resourcing | Mass Link Project Task Assignments.
- [Optional] Click
to open and close the Filters. Select the filter criteria to filter the project task assignments and click Apply. The project task assignments that meet your criteria are displayed. See Mass Link Project Task Assignment Fields in Lightning for more information.
- Click Clear to remove the applied filters.
- From the Resource Request to Link or Assignment to Link lookups, select the resource request or assignment, or both that you want to link the assignments to.
- The Resource, Role, Start Date and End Date in the read only fields and filters are automatically populated with the details of the resource request or the assignment selected from the lookups.
- Select the project task assignments you want to link.
- Click Link Project Task Assignments.