Creating Project Versions and Baselines
To create a project version A read-only data capture of the project in a particular moment in time. or baseline A static data capture of the original or re-planned project against which changes are compared.:
- On a project record, click Actions | Project Versioning | Create Version. The Create Version window opens.
- Complete the fields, as needed. Version Name is the only mandatory field. The fields are described in Create Project Version Fields.
- [Optional] To set the version as the project baseline A static data capture of the original or re-planned project against which changes are compared., select the Baseline checkbox.
- Click Create.
Baseline Versions
You can have only one project version as your baseline, and you cannot delete project baseline versions. To change the baseline status for a version, either:
- Create another version, as above, and select the Baseline checkbox. This version replaces the previous version as the baseline.
- Edit the existing baseline version and deselect the Baseline checkbox.To do this:
- On the relevant record in the Managed Versions related list, click
- Click Edit.
- Deselect the Baseline checkbox.