Managing Smart Rescheduling
Use the fields in the Smart Rescheduling Settings custom setting to customize the behavior of Smart Rescheduling. For more information about Smart Rescheduling, see Smart Rescheduling Overview.
| Field | Description | Default Value |
|---|---|---|
| Allow Application if Budget Exceeded | If selected, you can still apply the suggested adjustments, but you are informed that doing so will result in your project's budget being exceeded. This setting is not applied if either the Cannot Apply Suggested Adjustments or Display Budget Exceeded Message Only custom setting fields are also selected. | Deselected |
| Cannot Apply Suggested Adjustments | If selected, suggested adjustments cannot be applied to the Work Planner, but they can still be edited and exported in the Suggested Adjustments window. | Deselected |
| Display Budget Exceeded Message Only | If selected, you are informed that you cannot apply the suggested adjustments because doing so will result in your project's budget being exceeded. This setting is not applied if the Cannot Apply Suggested Adjustments custom setting field is also selected. | Deselected |
SECTIONS