Including Role Request Cost and Revenue Amounts in the Estimate Financial Summary
The Estimate Financial Summary provides a monthly view of total cost and revenue for the estimate. These totals include cost and revenue relating to role requests on the estimate.
If a role request has a rate card with a static cost or bill rate, the number of hours per month might vary but its hourly rate does not change. If a role request has a rate card with dated resource cost or bill rates, the number of hours per month might vary, and its hourly rate might change over the estimate's duration. Any variation in a role request's hours or rates is accounted for in the summary totals, as illustrated by the examples that follow.
The following examples are based on a simple estimate with one role request where the FTE (%) is 100%. In both examples, the role request starts on June 1, 2026 and ends on September 30, 2026. Eight hours are worked daily Monday - Friday, and there are no schedule exceptions. The number of working days and hours per month are therefore: