Updating Multiple Plans with the Latest Data from Analytics

You can schedule a mass update from Analytics for the default scenario created from and linked to a data source. This eliminates the need for manual updates, ensuring data is kept current across multiple forecasts automatically. Use filters to select the scenarios and set the specific time for the update process.

You can configure the mass update to overwrite plan data to match the Analytics dataset. For any plan with the Delete Obsolete Plan Data setting enabled, the process deletes obsolete dimensions, measures, and cell values for all scenarios. Adjustments and comments linked to the deleted cells are also removed. However, a cell that has an active adjustment is retained, along with its comment, even if the cell is obsolete in the dataset. For more information, see Creating a Plan Template and Creating a Plan from a Data Source.

Notes:
  • A cell that contains an active adjustment is retained when you update from Analytics, even when the cell is empty in the dataset and the Delete Obsolete Plan Data setting is enabled. Any comment on the cell is also retained. If the dataset later provides a value for the cell, the adjustment is added to that value.
  • An adjustment is active if its expiration date:

    • Is not defined
    • Is set to today's date
    • Is set to a future date
  • Your saved row, tree-row, and column order for the scenario is preserved when it's updated. If the process identifies columns that don't already exist in the plan, the new columns are inserted in alphabetical order relative to the existing columns rather than appended to the end.

To complete the Mass Update from Analytics process:

  1. From the Planning Task Launcher tab, click Update from Analytics. The Update from Analytics wizard displays.
  2. In the Filters section, search for your default scenario by selecting the input data source used to create the scenario. If required, you can also apply further filters, such as plan name, category, sub-category, or label, to narrow down your search.
  3. Click Apply. The plans selected based on the filtering criteria appear in the Plans section. To add or remove a plan from the list, adjust your filters and click Apply, or click Clear to remove all filters.
  4. Click Next.
  5. [Optional] Select the Override Formulas checkbox. Selecting this checkbox replaces the data in plan cells created by formulas with updated data from the selected Analytics data source.
  6. Select the Schedule Update from Analytics checkbox.
  7. If you want to run the process immediately and only once, deselect Schedule Update from Analytics and proceed to the next step. Otherwise, define the schedule for future executions of the process. To define the schedule:

    1. Ensure that Schedule Update from Analytics is selected.
    2. For Schedule Frequency, select one of the following:

      • Hourly: if you want the process to run every hour.
      • Daily: if you want the process to run once every day.
      • Weekly: if you want the process to run on specific days of the week. You can then select the days.
      • Monthly: if you want the process to run once every month. You can then select a monthly method to determine on which day of the month the process runs.
    3. For Schedule Start Time, select the preferred hour when you want the process to run.

      Note:

      Only the hour part of your selection is used, the minutes are ignored. This is because the system checks for scheduled processes every hour on the hour and then executes them. If multiple jobs are found for the same hour, they are grouped and chained, running sequentially in the following order: Create Multiple Plans, Update from Analytics, and Send to Analytics.

  8. Click Save. The Mass Update from Analytics process is scheduled.