Scheduling the Process to Update Forecasts with the Latest Data

You can schedule the process to keep your forecasts up to date with the latest operational data available in the Services Forecast Live dataset.

Notes:
  • Administrators can define the number of forecasts updated in a single process using the Multi-Plan Update Process Size field on the Planning Chunk Size Settings custom setting. The maximum limit is 5,000. For more information, see Planning Chunk Size Settings Fields.
  • When the data is updated, any cell that has an active adjustment is retained, along with any comment on that cell. An adjustment is active if its expiration date:

    • Is not defined
    • Is set to today's date
    • Is set to a future date

To schedule the process:

  1. From the Planning Task Launcher tab, click Update from Analytics. The Update from Analytics wizard displays.
  2. In the Filters panel, for Input Data Source, select "Services Forecast Live". This ensures that all forecasts are processed.
  3. Click Apply. The Plans table refreshes to display all your forecasts.
  4. Click Next. The Select Settings page of the wizard displays. This page enables you to schedule future executions of the process.
  5. Define the schedule for future executions of the process. To do this:

    1. Ensure that Schedule Update from Analytics is selected.
    2. For Schedule Frequency, select one of the following:

      • Hourly: if you want the process to run every hour.
      • Daily: if you want the process to run once every day.
      • Weekly: if you want the process to run on specific days of the week. You can then select the days.
      • Monthly: if you want the process to run once every month. You can then select a monthly method to determine which day of the month the process runs on.
    3. For Schedule Start Time, select the preferred hour when you want the process to run.

      Note:

      Only the hour part of your selection is used, the minutes are ignored. This is because the system checks for scheduled processes every hour on the hour and then executes them. If multiple jobs are found for the same hour, they run one at a time, in the order in which their schedules were created. Any job that does not run within its hour stays queued and runs first in the next hour.

  6. Click Save. The forecasts are updated with the latest data each time the process runs. You can monitor its execution from the Asynchronous Process Jobs tab.

You can also select the Needs Full Recalculation field on a forecast so that all of its calculated values are recalculated the next time the process runs. For more information, see Updating Forecasts with the Latest Data On Demand.