Updating Forecasts with the Latest Data On Demand

A scheduled process periodically runs to keep your forecasts up to date with the latest operational data available in the Services Forecast Live dataset. You can manually run this process if you cannot wait for the next execution.

Notes:
  • Administrators can define the number of forecasts updated in a single process using the Multi-Plan Update Process Size field on the Planning Chunk Size Settings custom setting. The maximum limit is 5,000. For more information, see Planning Chunk Size Settings Fields.
  • When the data is updated, any cell that has an active adjustment is retained, along with any comment on that cell. An adjustment is active if its expiration date:

    • Is not defined
    • Is set to today's date
    • Is set to a future date

To update forecasts with the latest data:

  1. From the Planning Task Launcher tab, click Update from Analytics. The Update from Analytics wizard displays.
  2. In the Filters panel, for Input Data Source, select "Services Forecast Live". This ensures that all forecasts are processed.
  3. Click Apply. The Plans table refreshes to display all your forecasts.
  4. Click Next. The Select Settings page of the wizard displays. This page enables you to schedule future executions of the process.
  5. Deselect Update from Analytics.
  6. Click Save. The forecasts are updated with the latest data in a background process. You can monitor its execution from the Asynchronous Process Jobs tab.

Recalculating All Calculated Values

In rare cases, a subtotal or formula in a forecast can hold a value that is no longer correct. Because the value is not marked for recalculation, updating the forecast does not correct it when the data in the dataset has not changed.

To correct these values, select the Needs Full Recalculation field on the affected forecast's records.

You can select the field when you edit the record, from a list view, or using Data Loader. The field is editable for users assigned the WorkGrid - Manage Data Sources and Plans permission set. Your administrator must add the field to the page layout before it displays on the record. For more information about editing page layouts, see the Salesforce Help.

The next time the forecast is updated with the latest data, every calculated value in it is recalculated, even if no values change in the dataset. This happens whether the update runs on demand or as part of the scheduled process.

Notes:
  • When the recalculation completes successfully, the Needs Full Recalculation field is deselected. If the recalculation fails, the field remains selected and the recalculation runs again in the next update.
  • A locked forecast is not recalculated until it is unlocked.
  • If more forecasts have the field selected than a single update process can handle, the field remains selected on the forecasts that were not updated to enable recalculation in a later update.
  • The recalculation runs as an asynchronous plan job of type "Recalculate Cells". If the Needs Full Recalculation field on a forecast remains selected after an update, check the plan jobs for the forecast to find out why the recalculation did not finish.