Updating Forecasts Using a Plan Template

You can update one or more existing forecasts to match the current structure of a plan template. This is useful when a template has changed since your forecasts were created. For example, if a new measure or summary card was added, and you want your existing forecasts to use it without deleting and recreating them.

Updating a forecast overwrites its structural definition, including any additive measures and summary cards and its layout, with the template's current definition. Cell-level adjustments, comments, and version history are not affected.

To update forecasts using a template:

  1. From the Planning Task Launcher tab, click Update Multiple Plan Definitions. The Update Multiple Plan Definitions wizard displays.
  2. Select Plan Definitions.
  3. In the Filters panel, filter the list of forecasts as needed. Select a plan template from the Plan Template filter to show only forecasts linked to that template.
  4. [Optional] Select Show Only Outdated Plans to show only forecasts whose template version is older than the current version of their linked template, or that have never been updated to their template's current version.
  5. Select an output datasource from the Output Datasource filter to narrow the list further.
  6. Click Apply. The Plans table refreshes to display the forecasts that match your criteria, along with each forecast's current template version and output datasource.
  7. Select the forecasts that you want to update.
  8. Click Next.
  9. Search for and select the plan template that you want to update the selected forecasts with.
  10. Click Save. The process to update the compatible forecasts runs in the background.

If any of the selected forecasts can't be updated with the selected template, they are listed in the Incompatible Plans window along with the reason. For example a mismatched dimension, a removed measure, or a removed summary card. Incompatible forecasts are excluded from the update automatically.

Forecasts that are skipped or fail during the update are reported on the Async Process Jobs tab so that you can review them and run the process again if needed.