Adding a Task or Checkpoint

Professional Services Cloud

You can add a project taskClosed or a checkpointClosed to a projectClosed using the Tasks pane or the Context menu.

To add a project task or checkpoint to a project using the Tasks pane:

  1. Select the project to which you want to add a task.
  2. Select a task on the Schedule or Task pane under which you want the new task to appear.



  3. Click Create New Task to add the task to the Schedule pane.
  4. Enter a name for the task.
  5. Select or enter the Start and End dates of the task.
  6. [Optional] Enter a duration in the Duration cell.
    Tip:

    If you want a checkpoint, set the duration to zero days.

  7. [Optional] In the Points cell, enter the estimated effort, in points, required to complete the task.
    Note:

    You must ensure that the Points field contains a number greater than or equal to zero. If you use planning pokerClosed to estimate effort or the relative size of a task, we recommend entering a number in the Fibonacci sequenceClosed such as 0, 1, 2, 3, 5, 8, 13, 21, 34, 55 or 89.

  8. If you want to assign one or more resources or roles to the task:
    1. Click the Assigned Resources cell.
    2. Click Add another resource.
    3. Select the name of the resource or enter some characters from their name. You can assign a resource who is external to your PSA organization (an external resource): enter their name, press Enter or click OK, and click Assign when the Confirm External Resource popup window appears.
    4. Select a Resource Name cell and select an option in the drop-down list from those available in your organization.
    5. Repeat the step above for the role you want.
    6. Add more resources and roles if required.
    7. Click Apply Changes.
    8. Note:

      This action creates a project task assignment not a resource assignment. Depending on the configuration that your administrator has chosen, resources can enter time against this project task. If you want the resource to book time and expenses to the project, you must also assign them to the project. See Searching for Resources and Entering Time Against Project Tasks.

  9. If you want to associate the project task with a milestone on the project:
    1. Click the Milestone cell.
    2. Select a milestone from the drop-down list.
  10. Click Save.

To add a project task or checkpoint using the context menu:

  1. Select the project to which you want to add a task.
  2. Right-click a task in the Task pane or the Schedule pane or right-click the bottom of either pane.
  3. Hover over Add and then do one of the following:
  4. Enter a name for the task and complete the remaining fields in the Tasks pane.
  5. Click Save.