Using the Staffer

To staff the resource requests for your project using the Staffer:

  1. Ensure that you have set the appropriate permission controls for resource request entry and staffing for your resources, regions, practices, groups and projects.
  2. Ensure you have created the resource requests for your projects and they are marked Ready to Staff.  
    Tip
    If your resource request does not appear in the Staffer, it could be because its status is not set to Ready to Staff.
  3. Click Staffer on the sidebar.

    The staffer appears with all resource requests in the Resource Requests section. All the resource requests for which you have permission controls are listed.

  4. Locate the resource request that you want to staff. You can narrow the list of resource requests by:
  5. Click the resource request.

    The resource request appears in the Worksheet and a green bar appears, which represents the requested schedule. You can zoom in or out on the calendar time periods by clicking the magnifying glass icons on the right.

  6. Locate the resource that you want to assign to the resource request. You can narrow the list of resources by:
  7. Click a resource.

    The worksheet underneath the resource request is displayed, along with a visual representation of that resource's availability:

  8. If you want to change the schedule pattern for the assignment, select the schedule pattern you want from the Schedule Pattern drop-down list. For further information, see "Staffer Fields".
  9. Double-click the resource you want to assign in the Worksheet section.

    The Plan tab appears with the details for that resource.

  10. To assign the resource, click Schedule. To hold the resource, click Hold.
  11. Click Save.
  12. Repeat steps 6 to 11 for each resource that you want to assign to the resource request.
Tips
To view an assignment, resource request or resource on its detail page, right-click its name and click Open Record.
You can drag headings to view the fields in the order that you want.
Note
If you click your browser's back button while using the Staffer, it returns to the PSA page you were on before you started the Staffer.

Related Information

Resources

Resource Requests

About the Resource Planner

About Staffer

Assignments and Schedules

Related Tasks

Setting up Resources

Creating Resource Requests

Using the Resource Planner

Reference Materials

Resource Fields

Resource Request Fields

Assign Resource to Project Fields

Copy Resource Requests from Project Templates Fields

© Copyright 2009-2012 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.