Time Variance Settings
Time variance functionality is controlled using these fields in the Time Variance Settings custom settings.
Setting | Description |
Default |
---|---|---|
|
Specifies the time variance The difference between a resource's scheduled working hours and the hours worked per calendar week. over scheduled working hours to include in time variance calculations. | 0 |
Allowed Variance Under | Specifies the time variance The difference between a resource's scheduled working hours and the hours worked per calendar week. under scheduled working hours to include in time variance calculations. | 0 |
Exclude Billable Hours | If selected, billable hours are ignored when calculating Time Variance. | False |
Exclude Credited Hours | If selected, credited hours are ignored when calculating Time Variance. | False |
Exclude Excluded Hours | If selected, excluded hours are ignored when calculating Time Variance. | False |
Report All | Specifies that time variance The difference between a resource's scheduled working hours and the hours worked per calendar week. calculations include details on all resources, including resources who do not show outside the allowed variance ranges. | False |
Use Percentage | If true, the values in the Allowed Variance Over and Allowed Variance Under settings are percentages of time variance The difference between a resource's scheduled working hours and the hours worked per calendar week.. If false, the values in the Allowed Variance Over and Allowed Variance Under settings are hours. This setting is false by default. | False |