Managing Project Tasks from Gantt on a Project Record
Before you can view Gantt from a project record page, your administrator must:
- Add the PSA Project Gantt Lightning component to the Project Lightning record page. For more information, see Setting up the Project Gantt Lightning Component
- Grant you the required permissions. For more information, see Permissions for the Project Gantt Lightning Component
You can view the following in Gantt format from a project record without opening Gantt:
- Project tasks.
- Project task hierarchy.
- Any dependencies between tasks.
- The work calendar associated with a task.
-
Project task assignments and the resources or resource roles assigned, including external resources. Avatars enable you to see at a glance who is assigned to a task:
- Avatars show the profile image of the user referenced in the Salesforce User field of the resource’s contact record, provided you have the required permissions.
- A is shown if there are more assigned resources than can be displayed.
- If an avatar is not available for an assigned resource or if the resource is an external resource, the resource's initials are displayed.
- If there is no resource assigned but there is a role assignment, the initials of the role are displayed. For example, if the role is project manager, PM is displayed.
- If you hover over an avatar or any initials, the relevant resource names or roles are displayed.
Provided editing has not been disabled by an administrator and you have the relevant field permissions, you can update any supported field types on project tasks. For more information, see Editing Text on Project Tasks and Changing Start and End Dates on Project Tasks.
Viewing Project Tasks
To bring a project task into view on the Gantt chart, click the project task name on the relevant row. If you hover over a project task, a tooltip is displayed containing the task name and the start and end dates.
Child tasks are displayed underneath their parent tasks on the Gantt chart. The start and end dates of parent tasks reflect the details within the child tasks. For more information on how the tasks are displayed, including the color-coding, see Gantt Chart Controls.
If a work calendar A calendar that defines the working days, hours and public holidays for a resource, region, practice or group. is associated with the project or a project task, any non-working time is shaded gray on the Gantt chart. The work calendar associated with a task is displayed in the Work Calendar column in the Gantt grid and can be edited from there if required. If the work calendar column is not visible, contact your administrator. For more information about work calendars and holidays, see About Time Periods, Work Calendars, and Holidays and Using Work Calendars in Gantt.
If is selected in the toolbar, days or date ranges when resources are over allocated are shaded in gray with a red outline on the Gantt timeline. For more information, see Identifying Over Allocated Resources.
Managing Columns in the Gantt Grid
To reorder columns in the Gantt grid, drag them into the required position.
To hide columns that contain information you don't need, right-click the column heading and select Hide column. To show a hidden column, right-click any column heading and select the column you want to show from the Columns sub-menu.
To ensure that key columns in the grid always remain in view while you are reviewing or editing information in other columns, you can move columns to a locked position in the left part of the grid. To do this, right-click the column heading and select Move column to locked. To unlock a previously locked column, right-click the column heading and select Move column to unlocked. The column containing error and warning icons is always locked in the left part of the grid and cannot be moved. The Name column is locked in the left part of the grid by default but can be unlocked and moved if required.
Viewing Record Details
To view more information about a project task from the Gantt chart on a project record, do one of the following:
- Select the task and click .
- Double-click the project task's bar on the Gantt chart.
The information is displayed on the Task tab in a Record Details panel. The fields on the Task tab are controlled by your administrator. Any details you don't have permission to view are omitted.
To view details of resources that are related to the currently selected task, you can switch from the Task tab to the Resources tab in the Record Details panel. Alternatively, you can double-click a resource's avatar or initials that are displayed in the Assigned Resources column to open the Resources tab in the Record Details panel. You cannot view details of external resources or a resource's role.
You can also view the information associated with the assigned milestone in the Milestone tab.
The following fields are displayed by default in the Milestone tab:
- Name
- Status
- Target Date
For information on permissions, see Permissions for the Project Gantt Lightning Component.
For more information about the Record Details panel, see Viewing Record Details.
Changing the Gantt Chart Calendar View
The default view available is Months but you can change it to Days, Weeks, Quarters, or Years. The option you select is retained between browser sessions.
To center the view on the current date, click Today.
Expanding or Contracting the Gantt Chart
To expand or contract the Gantt chart:
- Click to expand the Gantt chart to full view.
- Click to return it to its original size.
Expanding or Collapsing All Project Tasks
To expand or collapse all the project tasks displayed on the Gantt chart:
- Click to expand all the project tasks.
- Click to collapse all the project tasks.
Searching for a Project Task
To search for a project task using the Search field in the toolbar, start typing characters from anywhere in the project task name. PSA searches the tasks on the current project and narrows down the search results as you type. If you can't find a project task, check your filters as they might be filtering out the task you are looking for.
Identifying Over Allocated Resources
From Gantt on a project record, you can see immediately when a project task has over allocated resources so that you can take action to reduce potential delivery risks on the current project. To show or hide details of over allocation, click in the toolbar. If is not available, contact your administrator.
Over allocation is indicated in the following ways:
- Days or date ranges when resources are over allocated are shaded in gray with a red outline on the Gantt timeline. If you hover over the header at the top of the shading, a tooltip lists the resources who are over allocated during that day or date range.
- is displayed in a row containing a project task with resources assigned who are over allocated during that task. If you click , a list of the over allocated resources is displayed.
For additional information on how tasks are displayed in Gantt on a project record, including color-coding, see Gantt Chart Controls.
Editing the Work Calendar on a Project Task
To edit the work calendar associated with a project task:
- Click the relevant cell in the Work Calendar column of the Gantt grid.
- Select the relevant work calendar from the drop-down list. Only the work calendars associated with this project are available for selection.
- Click Save. Your changes are displayed in the Gantt grid and the corresponding project task record is updated.
Editing Text on Project Tasks
To add or edit text on a project task:
- Double-click the relevant cell in the Gantt grid. When you hover over a cell, indicates it is editable and indicates it is not editable.
- Type in your text or overtype existing text. The edited cell is highlighted when you click away from it in the grid.
- [Optional] Update text on other project tasks.
- Review your changes.
- [Optional] Click in the toolbar to revert the data to the last saved state and discard all of the changes indicated by the highlighted cells.
- Click Save. Your changes are displayed on the Gantt chart and the corresponding project task records are updated.
Changing Start and End Dates on Project Tasks
The following rules apply when changing project task start and end dates:
- You cannot move any tasks if editing has been disabled by an administrator.
- You cannot move parent tasks, only child tasks.
- A parent task must encompass the start date of its earliest child task and the end date of its latest child task. This means if you move a child task to a date that is earlier than the parent task's start date or later than the parent task's end date, the parent task automatically extends to cover the child's new date.
- Dependencies between tasks are taken into account. You cannot move a task to start before the end date of the task it is dependent on. Any lag set on a dependency is observed where possible. For more information on dependencies between tasks, see Managing Project Task Dependencies.
You can change project task start and end dates from Gantt on a project record in the following ways:
- By dragging and dropping a child task bar horizontally on the Gantt chart, keeping the length of the task the same.
- By dragging the right edge of a child task bar horizontally to a different end date on the Gantt chart, extending or contracting its length. To change the start date of a child task, drag it to your chosen start date first, then drag the right edge of the task horizontally and release it when it reaches the required end date.
- By changing the dates displayed in the Start Date and End Date columns on the corresponding child task's row in the Gantt grid.
Using Start No Earlier Than Markers
Bars representing project tasks in the Gantt chart have small, gray Start No Earlier Than markers on the lower left corner. If you try to move a task to a date that is not possible because of the Changing Start and End Dates on Project Tasks, the Start No Earlier Than marker moves to that position on the Gantt chart but the task itself doesn't move. The marker acts as a reminder that you would like the task to start then.
These markers are useful because they allow you to map potential dates for tasks on the Gantt chart, even if you cannot move the tasks yet. If you hover over a marker, a tooltip is displayed with details of the corresponding Start No Earlier Than date.
If a move is not allowed because the task you want to move is a dependent task, move the task that is blocking the move to an earlier date and then try moving the dependent task again.
Updating Start and End Dates by Dragging Tasks on the Gantt Chart
To change the start or end date of a task by dragging it on the Gantt chart:
- Drag the task horizontally on the chart to your chosen start date without changing its length. You cannot drag parent tasks.
- [Optional] Increase or decrease the length of the task by dragging the right edge of the task horizontally and releasing it when it reaches the required end date.
- [Optional] Drag other child tasks to change their start and end dates.
- Review your changes.
- [Optional] Click to return the Gantt chart to its last saved state and discard all of the changes you have made. Changes are indicated by highlighted cells in the Start Date and End Date columns in the Gantt grid.
- Click Save.
Updating Start and End Dates by Changing Task Dates in the Gantt Grid
To change the start date or end date of a task by amending the dates in the Start Date and End Date columns in the Gantt grid:
- Double-click the cell in the grid you want to update and select a date from the calendar. Updated cells are highlighted to indicate unsaved changes.
- [Optional] Update other cells in the Start Date and End Date columns, as required.
- Review your changes. You can view the bars representing the tasks in the Gantt chart to see the effect.
- [Optional] Click to return the Gantt chart to its last saved state and discard all of the changes you have made.
- Click Save.
Viewing Project Status and Performance
You can view a project’s status and performance on the Gantt chart by comparing the start and end dates of the project tasks in the baseline version with those of the project task:
- Click and select Baseline.
- The baseline bar appears on the Gantt chart. You can compare the project task dates in the baseline with that of the existing project task from the tooltip details displayed when you hover over the bars.
The following details are displayed in the baseline bar tooltip:
- Baseline (Version Name)
- Project Task Name
- Start Date
- End Date
- A warning if the project task has a delayed start or has overrun
The following color-coding is used on the baseline bar:
- Blue: the project task is in the neutral status and running on time.
- Green: the project task is running ahead of time.
- Orange: the project task is delayed or has overrun.
You can also compare the actual dates of the project tasks with their planned dates and analyze the status of the project task:
- Click and select Actual Dates.
- The actual dates bar displays on the Gantt chart. You can compare the actual dates of the project task with its planned dates from the tooltip details displayed when you hover over the bars.
The following details are displayed in the actual dates bar tooltip:
- Actual Dates
- Project Task Name
- Start Date
- End Date
- A warning if the project task has a delayed start or has overrun
The following color-coding is used on the actual dates bar:
- Blue: the project task is in the neutral status and running on time.
- Green: the project task is running ahead of time.
- Orange: the project task is delayed or has overrun.
You can also select both the Baseline and Actual Dates options together to compare them with the project task.
Viewing the Critical Path
To show or hide the critical path The longest path of planned activities to the end of the project. This shows the earliest and latest each task can start and finish without making the project longer. This is the shortest time in which the project can be completed. of the current project in Gantt, click . If the button is not available, contact your administrator.
When the critical path is displayed, tasks that end on or after the project end date and any dependent tasks are highlighted.
For more information on the critical path and dependencies, see Using Critical Path in Gantt and Managing Project Task Dependencies.
Filtering Project Tasks
You can use the filter panel to focus on the project tasks you want to view:
- Click to open the filter panel.
- Specify the filters you want to apply to the project tasks displayed in Gantt on a project record.
- Click Apply.
- [Optional] Click Reset to revert to the default filter values
- [Optional] Click to close the filter panel.
The Resource Role and External Resource fields are available for multi-selection. In the Resource Role field, you can select multiple resource roles to filter by. In the External Resource Field, you can select multiple external resources attached to the current project's Project Task Assignments when filtering.
Saving Filter Sets
To save your filter selections in a new filter set:
- Select the required filters.
- Click Save As in the filter panel menu.
- Enter a name for your filter set.
- Select the required sharing settings for your filter set.
- Click Save.
You can also click Save in the filter panel menu to save filter selections to an existing filter set.
Your filter set is saved and displayed in the Saved Filters drop-down list in the filter panel. To make your saved filter set the default, click and select Set as Default.
Sharing settings can be set individually for each saved filter set. When saving or editing, select one of the following options:
- Only I can see this filter
- All users can see this filter
When filter sets are set to Only I can see this filter, other users cannot edit, delete, share, or save your filter sets. These options are hidden from other users.
To remove the default state from your filter set, click and select Remove Default.
Editing Filter Sets
To edit your filter sets in the filter panel:
- Select your required filter set from the Saved Filters drop-down list.
- Click , and then click Edit.
- [Optional] Rename your filter set and click Save.
- Edit the selected filters in the filter panel, as required.
- Click , and then click Save.
Your filter set is updated.
Deleting Filter Sets
To delete a saved filter in the filter panel:
- Select your required filter selection from the Saved Filters drop-down list.
- Click , and then click Delete.
- Click Delete to confirm.
The visibility of the Apply, Clear and Reset filter buttons changes, based on the actions performed in the filter panel:
- When you edit the filter values, the Apply, Clear, and Reset buttons display.
- After you apply changes to the filters, only the Reset and Clear buttons display.
- When a default filter set is selected, only the Apply and Clear buttons display.
- When no default filters are applied, no buttons are displayed.
The subtitle text for Gantt on a project record also updates according to the filters applied.
Exporting Data to Microsoft Project
To export the data to a file in XML format, click Export. You can then open the XML file in Microsoft Project 2013 or later. The following data is exported:
- Project details
- Project tasks
- Project task assignments and the resources or resource roles assigned, including external resources
- Project task dependencies
- Project work calendar
- Data in custom columns
Exporting Data in Custom Columns
Data in custom columns is mapped from Salesforce data types to Microsoft Project custom field types as shown in the table below.
Salesforce Data Type | Microsoft Project Custom Field Type | Notes |
---|---|---|
Address | Text | |
Boolean | Flag | |
Date | Date | |
Datetime | Date | |
Double | Number | |
Text | ||
Integer | Number | |
Location | Text | |
Long | Number | |
Lookup | Text | Lookup fields are exported using the lookup record’s name. For example, a lookup to a milestone called 50% Complete would export with the value 50% Complete. |
Phone | Text | |
Picklist | Text | Picklists are exported using the label of the picklist value. This means the same value might be exported differently depending on the label translation. Multi picklists are not currently supported. |
String | Text | |
Textarea | Text | |
Time | Text | |
URL | Text |
There is a limit to the number of custom columns you can export for each Microsoft Project custom field type.
Microsoft Project Custom Field Type | Maximum Number of Fields Available |
---|---|
Date | 10 |
Flag | 20 |
Number | 20 |
Text | 30 |
To view the data in an exported custom column in Microsoft Project, click the Add New Column column heading when viewing the exported data and select the relevant entry from the column selection list displayed.