Editing a Task Dependency Relationship
You can edit a task dependency relationship in the Schedule pane or in the Task Editor popup.
To edit a task dependency relationship in the Schedule pane:
- Double-click the arrow representing the relationship that you want to edit.
- Select the type of dependency that you want for the relationship. See Task Dependency Relationship Types.
- [Optional] Enter a lag This term is either a delay or an overlap between tasks in a dependency relationship. According to the dependency type, lag is added (or subtracted when a negative value) to the start or end time of the successor task. value in the Lag field.
- Click OK.
To edit a task dependency relationship using the Task Editor popup:
- In the Schedule pane, double-click the successor task of the dependency relationship that you want to change.
- Click the Predecessors tab.
- Edit the Task Name, Type and Lag fields of the dependency relationship that you want to change.
- Click Apply.