Deleting Tasks
You can delete project tasks A unit of work or collection of work associated with a project. and checkpoint A zero duration task record, which is used to represent an event in the project such as a key decision, completion of a work package, completion of a deliverable or end of a phase. Checkpoint tasks have no relationship with PSA milestones. tasks.
When you delete a project task:
- If it is a parent, all the child tasks below it in the hierarchy are deleted.
- If it is a child, the assignment is also removed.
- Time entered against it on the Time Entry page is also deleted.
- If it is the parent project, depending on the value of the DeleteProjectTasksWithProject configuration option, all of the project tasks in the project task hierarchy are also deleted.
To delete tasks:
- Select the tasks that you want to delete in the Tasks pane or the Schedule pane.
- Right-click the selected tasks.
- Click Delete Task(s).