About Task Dependency Relationships

In Project Task Gantt you can create a task dependency relationshipA relationship between two tasks. If a task is completed early or late, this has an effect on the start and end date of the task that succeeds it. between two tasks with one of these dependency types:

You can also specify a lagWhen a depenency relationship between project tasks exists, this term refers to the time gap added at the end of a task before the succeeding task can start. The default lag is 0. time on a task dependency relationship.

Notes
When you create a task dependency relationship in Project Task Gantt, the default lagWhen a depenency relationship between project tasks exists, this term refers to the time gap added at the end of a task before the succeeding task can start. The default lag is 0. time of 0 is applied.

You cannot create a dependency relationship between a parent task and any other task.

Concept Information

Project Task Gantt (Task Manager)

About Tasks

Related Tasks

Managing Projects

Viewing Tasks

Viewing Task Details in Salesforce

Changing Start and End Dates

Adding a Task

Adding a Task Dependency Relationship

Deleting a Task Dependency Relationship

Editing a Task Dependency Relationship

Assigning a Resource or Role to a Project Task

Closing Gantt Task Management

Deleting Tasks

Editing Project Task Details

Moving Tasks

Printing the Project Plan

Saving Changes

Searching

Undoing and Redoing Changes

Viewing the Critical Path

Zooming

Generating Resource Requests from Project Task Gantt

Associating Project Tasks with Milestones

Reference Materials

Project Task Gantt Fields

Project Task Gantt Settings

© 2009-2015FinancialForce.com, inc All rights reserved. FinancialForce and FinancialForce.com are registered trademarks, and the FinancialForce.com logo is a trademark. Other product names appearing herein may be trademarks.
This document contains proprietary information of FinancialForce.com, inc and its licensors, and is subject to change without notice.