In Project Task Gantt you can create a task dependency relationshipA relationship between two tasks. If a task is completed early or late, this has an effect on the start and end date of the task that succeeds it. between two tasks with one of these dependency types:
You can also specify a lagWhen a depenency relationship between project tasks exists, this term refers to the time gap added at the end of a task before the succeeding task can start. The default lag is 0. time on a task dependency relationship.
Concept Information
Project Task Gantt (Task Manager)
Related Tasks
Viewing Task Details in Salesforce
Adding a Task Dependency Relationship
Deleting a Task Dependency Relationship
Editing a Task Dependency Relationship
Assigning a Resource or Role to a Project Task
Generating Resource Requests from Project Task Gantt
Associating Project Tasks with Milestones
Reference Materials
© 2009-2015FinancialForce.com, inc All rights reserved. FinancialForce and FinancialForce.com are registered trademarks, and the FinancialForce.com logo is a trademark. Other product names appearing herein may be trademarks.
This document contains proprietary information of FinancialForce.com, inc and its licensors, and is subject to change without notice.