There are several ways that you can delete a task dependency relationship.
To delete a task dependency relationship using the context menu:
To delete a task dependency relationshipA relationship between two tasks. If a task is completed early or late, this has an effect on the start and end date of the task that succeeds it. in the Schedule pane:
To delete a task dependency relationship using the Tasks pane:
Concept Information
Project Task Gantt (Task Manager)
About Task Dependency Relationships
Related Tasks
Viewing Task Details in Salesforce
Adding a Task Dependency Relationship
Editing a Task Dependency Relationship
Assigning a Resource or Role to a Project Task
Generating Resource Requests from Project Task Gantt
Associating Project Tasks with Milestones