A project task is a unit of work with a duration, or a project checkpoint A zero duration task record, which is used to represent an event in the project such as a key decision, completion of a work package, completion of a deliverable or end of a phase. Checkpoint tasks have no relationship with PSA milestones., which has no duration. You can:
- Add, edit and delete project tasks and dependencies.
- Create and edit a project hierarchy.
- Assign resources and/or roles to project tasks to create project task assignments (PTAs).
- Create assignments or resource requests for PTAs.
- Synchronize project tasks with milestones.