Creating Assignments and Resource Requests from Gantt
For an overview of task-driven assignments and resource requests, see Task-Based Resourcing Overview.
When you have created assignments or held resource requests, you need to refresh Gantt for the details to be displayed.
To create assignments or resource requests from Gantt:
- Create the relevant PTAs, add estimated hours to the task, and then click Save.
- Click to open the relevant pages:
- To generate assignments, click the main part of the button to open the default Generate Assignments from Project Task Assignments page.
- To generate unheld or held resource requests, click the drop-down part of the button, and then select an option:
- Create Resource Requests. This opens the Generate Resource Requests from Project Task Assignments page, where you can create unheld resource requests.
- Create Held Resource Requests. This opens the Generate Held Resource Requests from Project Task Assignments page.